Project File · Public records
Every public record we have for Google data center campus, Stillwater
Stillwater, Payne County, OklahomaUnder constructionFirst public 2025Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 1 records · showing power and utility only ·
2026
Utility proceedingPending before the commissionJun 2026Oklahoma Corporation Commission
In the Matter of the Application of Oklahoma Gas and Electric Company for an Order of the Commission Approving its New Extra Large Load Tariff and Terms and Conditions of Service for Extra Large Load Customers and a Regulatory Asset to Recover Costs Associated with Portfolio Optimization Software
As proposed by OG&E: the Extra Large Load Tariff applies to new customers expecting demand of at least 75 MW, existing customers adding 75 MW of incremental demand or increasing demand above 125 MW, and existing customers whose profile changes to meet the 75 MW requirement. Terms proposed: a 15 year term with a maximum five year ramp up period, billing minimums, early termination and capacity reduction fees, and strong financial collateral requirements; large load customers pay upfront for 100 percent of the costs to connect to the grid, plus a monthly charge totaling $25 to $30 million per year to be credited to residential customers. Whether large load customers may supply their own or third party generation (the bring your own generation question) is the contested legal issue the Commission sent back for briefing.
PUD2026-000046
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
OG&E press release, paragraphs on applicability and terms (75 MW and 125 MW tests; 15 year term; five year ramp; billing minimums; termination and capacity reduction fees; collateral; 100 percent upfront connection costs; $25 to $30 million per year residential credit); case style from the OCC Daily Signing Agenda (October 2026), item VI
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1OG&E Proposed Large-Load Tariff Protects Oklahoma households
Oklahoma Gas and Electric CompanyTier 4 · Captured 2026-11-08 · Open the source - 2Investing $9 billion in Oklahoma's AI future (Google blog)
GoogleTier 4 · Captured 2026-11-08 · Open the source - 3Oklahoma energy affordability agreement (Google blog)
GoogleTier 4 · Captured 2026-11-08 · Open the source - 4Calendar Year 2025 New and Expanding Companies Report
Oklahoma Department of CommerceTier 1 · Captured 2026-11-08 · Open the source - 5Planning Commission Advances Google Data Center Final Plat
The StillwegianTier 3 · Captured 2026-11-08 · Open the source - 6U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source - 7OG&E Announces Landmark Contract With Google (press release)
Oklahoma Gas and Electric Company (PR Newswire)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page