Project File · Public records
Every public record we have for Google Red Oak data center
Red Oak, Ellis County, TexasOperatingFirst public 2023Filing entity: Alamo Mission LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
7 of 7 records
2026
Public decisionFiledOct 8, 2026Texas Department of Licensing and Regulation (TABS)
Texas Department of Licensing and Regulation (TABS), TABS2027003112
TDLR status as read 2026-11-09: Review Complete
- Estimated cost:
- $176 million estimated cost as filed with TDLR
- Floor area:
- 285,310 sq ft (as filed with TDLR)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
TABS project record TABS2027003112: "RED2A", 330 N. Austin Blvd, Red Oak, TX 75154, Ellis County; Owner: ALAMO MISSION LLC, 1600 Amphitheatre Parkway, Mountain View, CA; Design Firm: CORGAN; Scope: "NEW GROUND UP CONSTRUCTION BUILDING"; Square Footage 285,310 ft 2; Start Date 12/12/2024; Completion Date 12/12/2026; Estimated Cost $176,000,000
Air permitIssuedMar 27, 2026Texas Commission on Environmental Quality
Texas Commission on Environmental Quality, Federal Operating Permit (Title V) O4709; RN110852753
Issued March 27, 2026; expires five years from issuance
- Stated in the filing:
- Title V Federal Operating Permit O4709 issued March 27, 2026 to Alamo Mission LLC; permit expires five years from issuance
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Permit face: "FEDERAL OPERATING PERMIT IS HEREBY ISSUED TO Alamo Mission LLC, AUTHORIZING THE OPERATION OF Alamo Mission, Alamo Mission Data Center, Data Processing, Hosting, and Related Services, LOCATED AT Ellis County, Texas, Latitude 32 deg 31 min 54 sec, Longitude 96 deg 47 min 33 sec, Regulated Entity Number: RN110852753. Permit No: O4709, Issuance Date: March 27, 2026."
Utility proceedingPending before the commissionFeb 19, 2026Public Utility Commission of Texas
Joint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement
Net metering arrangement under PURA Sec. 39.916 pairing the Comanche Peak nuclear station with an Amazon Data Services data center load, inside ERCOT with Oncor as the interconnecting utility. Oncor’s October 2026 response to Commission Staff requests for information addressed evidence of SB 6 compliance; Order No. 11 (October 26, 2026) granted Oncor’s request for a decision on written submission. No terms are approved yet.
Docket No. 59399
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Index of filings: joint application of February 19, 2026; item 151 (Oncor response to Staff RFI Q 1-19, October 2026); item 167 (Order No. 11 of October 26, 2026); item 213 (latest filing, November 5, 2026)
2025
Utility proceedingDecidedOct 24, 2025Public Utility Commission of Texas
Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
Net metering arrangement under PURA Sec. 39.916 at a 265.5 MW point of interconnection: 180 MW of load available upon commercial operation and a further 85 MW within three years. The final order (April 23, 2026) approved the arrangement with conditions, which are binding on the applicants’ successors and assigns: the customer must fully curtail load within 30 minutes on ERCOT direction (automated where possible), may not participate in demand response programs or other ancillary services, the parties must report curtailments quarterly to ERCOT and Commission Staff for five years, and FGE must provide ERCOT ten days notice before maintenance or outages exceeding 5 MW.
Docket No. 58881
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Final order signed April 23, 2026, pp. 2, 6-9 (265.5 MW point of interconnection; 180 MW and 85 MW phases; 30 minute curtailment and reporting conditions); index of filings (joint application of October 24, 2025; rehearing motions filed May 18, 2026)
Public decisionFiledMay 15, 2025Texas Department of Licensing and Regulation (TABS)
Texas Department of Licensing and Regulation (TABS), TABS2025019071
TDLR status as read 2026-11-09: Inspection Complete
- Estimated cost:
- $176 million estimated cost as filed with TDLR
- Floor area:
- 170,594 sq ft (as filed with TDLR)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
TABS project record TABS2025019071: "RED1A", 330 N. Austin Blvd, Red Oak, TX 75154, Ellis County; Owner: ALAMO MISSION LLC, 1600 Amphitheatre Parkway, Mountain View, CA; Design Firm: Corgan; Scope: "New ground-up data center project. 170,594.00 sq ft"; Start Date 1/1/2023; Completion Date 5/15/2025; Estimated Cost $176,000,000
Air permitFiledJan 24, 2025Texas Commission on Environmental Quality
Texas Commission on Environmental Quality, Project 37459; Title V Permit O4709 application; RN110852753; CN605700061
Application accepted by TCEQ on January 24, 2025; start of operation then scheduled for early 2025
- Stated in the filing:
- Construction authorized under Permit by Rule Registration No. 167790 (January 27, 2022), updated under Registration No. 170469 (approved September 21, 2022); equipment: diesel-fired emergency engine/generator sets, emergency fire water pumps, diesel storage tanks, and mechanical draft cooling towers
- Stated in the filing:
- Diesel emergency generator sets in six groups (1, 1A, 2, 2A, 3, and 4) grouped by power rating and manufacturer; Form OP-UA2 engine kilowatt bands: Groups 1 and 1A at 2,237 kW and above, Groups 2, 2A, and 3 at 560 to 2,237 kW, Group 4 at 130 to 368 kW; selective catalytic reduction (SCR) fitted on Groups 1A and 2A; all engines Tier 2
- Stated in the filing:
- Major source of nitrogen oxides (NOx): potential to emit greater than 25 tons per year, the major-source threshold in the Dallas-Fort Worth ozone nonattainment area, which requires a Title V federal operating permit
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Initial Title V application package prepared by Trinity Consultants for Alamo Mission LLC. Section 1.2.1 gives the PBR history; the OP-1 form gives physical address 500 E. Ovilla Rd, Red Oak, TX 75154 and coordinates 32 deg 31 min 54.4296 sec N, 96 deg 47 min 33.0972 sec W; January 2025 correspondence in the package settles 156 North Austin Blvd as the address to list for the site.
No date in the record(rules in force and undated records)
Tax agreementNo date in the recordRed Oak
Tax abatement agreement (Texas Tax Code Chapter 312)
80% of real property and 100% of personal property abated
Draft research, not yet verifiedLast checked Nov 18, 2026Where it says this
Record ID 000022109; NAICS 518210
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Federal Operating Permit (Title V) O4709 issued to Alamo Mission LLC (Alamo Mission Data Center, Ellis County), with Statement of Basis
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2TCEQ Federal Operating Permit initial issuance application, Project 37459, Permit O4709 (Alamo Mission LLC, Alamo Mission Data Center, Red Oak, Ellis County)
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 3TDLR TABS project record TABS2025019071 (RED1A, Alamo Mission LLC, 330 N. Austin Blvd, Red Oak, TX)
Texas Department of Licensing and RegulationTier 1 · Captured 2026-11-09 · Open the source - 4TDLR TABS project record TABS2027003112 (RED2A, Alamo Mission LLC, 330 N. Austin Blvd, Red Oak, TX)
Texas Department of Licensing and RegulationTier 1 · Captured 2026-11-09 · Open the source - 5Chapter 312 Tax Abatement Agreements detail file (registry download), last updated 2026-10-10
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 6PUCT Interchange filing index, Project or Docket No. 58881
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 7PUCT Interchange filing index, Project or Docket No. 59399
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 8Texas - Google Data Center Locations (Midlothian and Red Oak, Ellis County)
GoogleTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page