Pine Island, Goodhue County, MinnesotaIn permittingFirst public 2024Filing entity: Ryan Companies US, Inc.Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 1 records · showing power and utility only ·
No date in the record(rules in force and undated records)
Utility proceedingDecidedNo date in the recordMinnesota Public Utilities Commission
Northern States Power Company (Xcel Energy) very large customer tariff under Minn. Stat. 216B.1622
Creates a very large customer class and tariff under Minn. Stat. 216B.1622. The class covers new loads of 100 MW or more, and any new customer of at least 20 MW but less than 100 MW that is system intensive, meaning it will require significant system modifications, design, engineering, or other expenditures prior to starting service. Very large customers take service in their own rate class under a minimum 15-year contract, including a five-year ramp-up period, with a minimum bill of at least 80 percent of the contracted amount and an exit charge on early termination. Costs are screened under an Incremental Cost Test with added filing rules; Xcel must report on how the electricity provided to each facility complies with the state's 2040 carbon-free standard. The Commission also directed Xcel to develop and propose a clean energy and capacity tariff under Minn. Stat. 216B.1623.
25-289
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
PUC very large customers page (class definition: 100 MW, plus 20 MW or more if system intensive; Docket 25-289); CUB Minnesota account of the decision (approval May 15, 2026; separate rate class; 15-year term with five-year ramp; 80 percent minimum bill; Incremental Cost Test; 216B.1623 directive)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Very large electric customers and the PUC process
Minnesota Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 2Data Centers to Pay Fair Share: PUC enacts protections for Xcel customers
Citizens Utility Board of MinnesotaTier 4 · Captured 2026-11-08 · Open the source - 3Xcel Energy to power new Google data center in Minnesota
Xcel Energy NewsroomTier 4 · Captured 2026-11-08 · Open the source - 4Pine Island settles lawsuit over hyperscale Google data center
Finance & CommerceTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page