Project File · Public records

Every public record we have for Google Papillion data center

Papillion, Sarpy County, NebraskaOperatingFirst public 2019Filing entity: Fireball Group LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

7 of 9 records · showing votes and minutes only ·

2026

  • Public decisionIssuedOct 21, 2026Nebraska Department of Water, Energy, and Environment

    Nebraska Department of Water, Energy, and Environment, ECMP document 20260099249

    Final determination DENYING Fireball Group, LLC's request for confidential treatment of its 2026 data center annual report information; the Department will make the records available to the public on the tenth day after receipt of the denial

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Letter of October 21, 2026 to Fireball Group, LLC (DWEE Facility ID 106518), via Michael S. Degan, Kutak Rock, 1650 Farnam St, Omaha

  • Public decisionFiledOct 1, 2026Nebraska Department of Water, Energy, and Environment

    Nebraska Department of Water, Energy, and Environment, ECMP document 20260061130; NDWEE Facility ID 106518

    Building floor area:
    1,140,958 square_feet
    General contractor:
    JE Dunn Construction
    Ndee facility identification number:
    106,518
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Report received 10/1/2026 under Neb. Rev. Stat. 70-1506(6): Section I facility identification; Section II campus footprint; Section III utility consumption (redacted); Section IV Nebraska Advantage statement

2023

  • Public decisionApprovedAug 29, 2023Sarpy County Board of Commissioners

    Sarpy County Board of Commissioners, Resolution 2023-270 (agenda item 23-425)

    Approves the First Amendment to the Meter Reading and Billing Agreement: from July 1, 2023, wastewater charges are based on the Adjusted Discharge Volume (MUD water volume minus cooling tower evaporation volume) until permanent discharge metering is agreed; the campus moves from the MUD Commercial rate to the county's Data Center rate

    Wastewater billing basis:
    Adjusted Discharge Volume = MUD Water Volume - Cooling Tower Evaporation Volume (from July 1, 2023)
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agenda item 23-425 summary and the First Amendment text (entered July 28, 2023; signed for Fireball Group LLC by Gary Demasi, Authorized Signatory)

2021

  • Public decisionApprovedJun 29, 2021Sarpy County Board of Commissioners

    Sarpy County Board of Commissioners, Resolution 2021-206 (agenda item 21-279)

    Approves the Meter Reading and Billing Agreement between Sarpy County and Fireball Group LLC: a metered system for measuring the campus's wastewater discharge into the Sarpy Sewer, with interim billing based on MUD water volume from September 18, 2020

    Water supplier:
    Metropolitan Utilities District (MUD)
    Wastewater rate terms:
    County data center rate; charges capped at the lowest rates paid by other non-governmental data center users of the county sanitary sewer system
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Resolution text: 'approved by a vote of the Sarpy County Board of Commissioners at a public meeting duly held ... on the 29 day of June 2021'; agreement Paragraph 2 metering from September 18, 2020

2020

  • Recorded voteMar 3, 2020Sarpy County Board of Commissioners

    Resolution 2020-073: Raven Northbrook, LLC (Gemini) Wastewater Connection Agreement and Service

    4 yes, 1 absent. Angi Burmeister (Commissioner): yes; David Klug (Commissioner): yes; Don Kelly (Commissioner): yes; Gary Mixan (Commissioner): absent; Jim Warren (Commissioner): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Minutes of March 3, 2020, item 5.6: IN FAVOR Commissioner Kelly, Commissioner Klug, Commissioner Burmeister, and Commissioner Warren; ABSENT Commissioner Mixan; RESULT Motion carried 4-0

2019

  • Public decisionIssuedFeb 13, 2019Google

    Google

    Announcement: Google is developing new data centers in Ohio and Nebraska as part of more than $13 billion in 2019 US investments

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Post text: 'We're announcing over $13 billion in investments throughout 2019 in data centers and offices across the U.S.' and, Midwest section, 'we're developing new data centers in Ohio and Nebraska'

No date in the record(rules in force and undated records)

  • Public decisionApprovedNo date in the recordSarpy County Board of Commissioners

    Sarpy County Board of Commissioners, Resolution 2018-336

    Approves the Sewer Connection and Wastewater Service Agreement between Sarpy County and Fireball Group LLC: terms of wastewater infrastructure improvements and connection of the development to the Sarpy Sewer

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Resolution 2023-270 recital: 'the County and Fireball Group, LLC ("Fireball") have previously entered into a Sewer Connection and Wastewater Service Agreement via Resolution 2018-336'; First Amendment recital A dates its execution October 30, 2018

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Sarpy County Board packet, August 29, 2023: Resolution 2023-270, First Amendment to the Fireball Group LLC Meter Reading and Billing Agreement (agenda item 23-425)
    Sarpy County, Nebraska
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    2026 Data Center Annual Reports Confidentiality Request: Final Determination (Fireball Group, LLC)
    Nebraska Department of Water, Energy, and Environment
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Nebraska Data Center 2026 Annual Report: Fireball Group LLC (NDWEE Facility ID 106518)
    Google LLC (filed with the Nebraska Department of Water, Energy, and Environment)
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Investing $13 billion in 2019 (Google announcement, February 13, 2019)
    Google
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Nebraska Tax Incentives Annual Report 2022
    Nebraska Department of Revenue
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Nebraska Tax Incentives Annual Report 2024
    Nebraska Department of Revenue
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Sarpy County Board Meetings minutes, March 3, 2020
    Sarpy County
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Nebraska Department of Economic Development FY2019-2020 Stakeholders Report (Google Papillion groundbreaking, $600M)
    Nebraska Department of Economic Development
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Inside the Site Selection Process (Google Project Wizard, Papillion, 275 acres)
    Greater Omaha Chamber
    Tier 2 · Captured 2026-11-08 · Open the source
  10. 10
    Nebraska data center locations (Lincoln, Omaha, and Papillion)
    Google
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    OPPD Board of Directors, All Committees Meeting package, August 18, 2026
    Omaha Public Power District
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page