Monrovia, Morgan County, IndianaApprovedFirst public 2025Filing entity: Woodland Caribou LLCLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

1 of 1 records · showing power and utility only ·

2026

  • Utility proceedingDecidedApr 22, 2026Indiana Utility Regulatory Commission

    Petition of Indianapolis Power & Light Company d/b/a AES Indiana for approval of a project required primarily to serve a large load customer, customer-specific arrangements, and an alternative regulatory plan (Google, Morgan County)

    First case decided under Indiana HEA 1007 (2025). Google’s data center in Morgan County (Monrovia) is served under a Customer Specific Contract of at least 15 years. Google committed to an 80 percent minimum demand obligation and its rates cover 100 percent of the annual energy, infrastructure, transmission and generation costs of serving it at that level; the filing included financial assurances and exit provisions against stranded costs. Infrastructure is built in phases aligned with actual demand. AES estimates about $770 million in customer savings over the plan. The serving project as filed is two battery storage systems (200 MW and 130 MW), a 130 MW solar array paired with a 130 MW battery, and a 10-mile 345 kV line to a new on-site substation.

    Cause No. 46394

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    AES Indiana release, 2026-10-07, Key elements bullets (100 percent cost coverage; 80 percent minimum demand; phased investment) and savings paragraph ($770 million estimate); AES Indiana release, 2026-04-23, Customer protections in the HEA 1007 filing (contract, financial assurances, minimum demand, exit provisions)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Votes and minutes

    Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    IURC Approves Customer-Protected Growth Plan to Serve Large Load Investment, Delivering an Estimated $770 Million in Customer Savings
    AES Indiana
    Tier 4 · Captured 2026-11-11 · Open the source · Archived copy
  2. 2
    AES Indiana and Google partner announcement (HEA 1007 filing)
    AES Indiana
    Tier 4 · Captured 2026-11-11 · Open the source · Archived copy
  3. 3
    A data center is coming to town (Project Louie, Morgan County)
    Indiana Daily Student / Arnolt Center for Investigative Journalism
    Tier 3 · Captured 2026-11-08 · Open the source
  4. 4
    Google behind 390-acre data center development in Morgan County, Indiana
    Data Center Dynamics
    Tier 3 · Captured 2026-11-08 · Open the source
  5. 5
    Indiana's new data-center cost law just passed its first test (AES Indiana / Google Monrovia)
    GridPermit (Backburner Labs)
    Tier 2 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page