Every public record we have for Google Mesa data center (Project Red Hawk)

Mesa, Maricopa County, ArizonaOperatingFirst public 2019Filing entity: Stone Applications LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

9 of 21 records · showing land and zoning rules only ·

2025

  • Zoning ruleIn effectDec 10, 2025Maricopa County

    Modernized Maricopa County Zoning Ordinance, data center provisions

    The modernized county zoning ordinance defines data centers and addresses them as an emerging technology use. Reporting on the adopted ordinance states that data centers are allowed in the IND-2 and IND-3 industrial districts, and land not zoned for the use must go through the county rezoning process. A county staff report for a February 2026 hearing states that data centers are a permitted use in the IND-2 district, while noting the ordinance does not specifically contemplate the use, which is why that project sought an overlay clarification.

    Maricopa County Zoning Ordinance (county ordinance P-18), text amendment TA25001

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    News release paragraphs on definitions for emerging technologies including data centers; staff report for cases CPA250009 and Z250027 (2026-02-11 hearing) on IND-2 permitted uses

  • Setback ruleIn effectJul 8, 2025Mesa

    Separation from residential districts, height cap, screening, parking, and sound studies for data centers

    Planning staff described a minimum separation of 400 feet from residential zoning districts or sensitive uses, measured from the data center property to the nearest residential property line, a maximum building height of 60 feet unless an exception is approved through a PAD, screening for mechanical equipment and substations, and parking at 1 space per 5,000 square feet for the first 200,000 square feet and 1 space per 10,000 square feet after that. Staff also described an initial sound study at the nearest residential property line, a post-occupancy sound study within 30 days of the certificate of occupancy, and annual sound studies for the first five years.

    Mesa City Code Section 11-31-36 (standards described by planning staff for Ordinance No. 5957, case PZ25057)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Staff presentation summaries for case PZ25057 (Planning and Zoning Board recommended approval 6-1 on 2025-06-25)

  • Development ruleIn effectJul 8, 2025Mesa

    Backup generator operation and testing notice, Data Centers

    An operator using backup generators must announce any routine operation, including testing, on its website and notify the City of Mesa Public Information Office at least 24 hours in advance. Outside a power outage or a utility demand response event, backup generators may run only between 9:00 a.m. and 5:00 p.m., Monday through Friday, excluding holidays. Systems that can run in parallel with the city electric utility or islanded are subject to a generator interconnection process and study at the operator's cost.

    Mesa City Code Section 11-31-36(G)(4)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Energy section, Example 4, quoting Section 11-31-36(G)(4)(a) to (e) verbatim

  • Development ruleIn effectJul 8, 2025Mesa

    Architectural features for data center buildings

    Every data center building must include at least five of twelve listed architectural features, such as overhangs, canopies, arcades, window shrouds, raised corniced parapets, tower elements, corner glass, sloped roof forms, murals, decorative grilles or screens, and architectural lighting. The standard aims at visual interest at entryways and areas the public sees.

    Mesa City Code Section 11-31-36(F)(5)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Design section quoting Section 11-31-36(F)(5), items i to xii

  • Development ruleIn effectJul 8, 2025Mesa

    Water Consumption and Thermal Management Report and Wastewater Report required with applications

    Every data center development application must include a Water Consumption and Thermal Management Report stating whether the facility is water-cooled or air-cooled, estimated water use in acre feet per year with a monthly breakdown, use in million gallons per day on a typical day and on the highest-use day, the highest instantaneous flow rate, whether high demand can shift to the city's low-demand periods, the number and size of water meters, and proof of a complete Sustainable Water Service Application. A Wastewater Report with proof of a complete Industrial User Survey under Title 8, Chapter 4 is also required.

    Mesa City Code Section 11-31-36(E)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Application requirements quoting Section 11-31-36(E), items 4 and 5

  • Zoning ruleIn effectJul 8, 2025Mesa

    Data Centers, Mesa Zoning Ordinance (Title 11)

    Data centers are allowed as an accessory use in commercial and employment districts and as a principal use in the General Industrial (GI) and Heavy Industrial (HI) districts, but a principal use data center is not allowed by right and needs approval of a Planned Area Development (PAD) Overlay District. A data center that serves only the on-site owner or tenant, does not lease services to third parties, and takes no more than 10 percent of the site's total gross floor area counts as an accessory use and is exempt from the section's standards.

    Mesa City Code Section 11-31-36 (added by Ordinance No. 5957)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Newsletter section on the data center ordinance; council minutes of 2025-07-08, item 8-h (Ordinance No. 5957); code text Section 11-31-36(A)(1) as quoted in the Lincoln Institute resource

2019

  • Development agreementApprovedJul 1, 2019City of Mesa

    City of Mesa, Legistar File 19-0809; approved by Resolution No. 11372

    Approved and authorized by Resolution No. 11372 on July 1, 2019

    Milestone minimum capital investment:
    $800 million
    Water allowance initial:
    1,120 acre_feet_per_year
    Milestone minimum taxable construction costs:
    $240 million
    Full time employee average compensation minimum:
    $65,000 _per_year
    Milestone minimum building gross area:
    500,000 square_feet
    Milestone minimum building gross area:
    250,000 square_feet
    Milestone minimum capital investment:
    $600 million
    Milestone minimum capital investment:
    $1 billion
    Milestone minimum taxable construction costs:
    $180 million
    Milestone minimum taxable construction costs:
    $300 million
    Water allowance maximum:
    4,480 acre_feet_per_year
    Acres:
    186 acres
    Milestone minimum building gross area:
    750,000 square_feet
    Water service peak hour capacity:
    333.3 thousand_gallons_per_hour
    Wastewater peak hour capacity:
    208 thousand_gallons_per_hour
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Development Agreement, parties clause; Recitals A-C; Sections 4.1-4.12, 5.1, 5.4, 6.1-6.6

  • RezoningApprovedApr 1, 2019City of Mesa

    City of Mesa, ZON19-00016; Ordinance No. 5502

    Rezoned 187 acres (7100 to 7600 blocks of East Elliot Road; 3100 to 3500 blocks of South Sossaman Road) from LI-PAD-PAD and PEP-PAD-PAD to EO, creating the Red Hawk Employment Opportunity Zone

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Legistar matter 13330 (ZON19-00016 Redhawk), MatterTitle and MatterPassedDate; council report Background section

No date in the record(rules in force and undated records)

  • Development ruleIn effectNo date in the recordMesa

    Offensive, Excessive, and Prohibited Noises, land use sound level limits

    Mesa's general noise chapter sets limiting sound levels by land use district in Table 1, measured as Leq: 60 dBA in residential districts, 65 dBA in commercial or business districts, and 70 dBA in agricultural and industrial districts. Noise exceeding the district level by 5 dBA or more counts as excessive noise under Section 6-12-3, and Section 6-12-4 sets measurement criteria.

    Mesa City Code Title 6, Chapter 12, Sections 6-12-1 to 6-12-6 (Table 1 in Section 6-12-5)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 6-12-5(A), Table 1, Limiting Sound Levels for Land Use Districts; Section 6-12-3; Section 6-12-4

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
    City of Mesa, Office of Economic Development
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
    City of Mesa (Legistar)
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Arizona Technology Council article on the Mesa data center standards
    Arizona Technology Council
    Tier 3 · Captured 2026-11-07 · Open the source
  8. 8
    Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
    Lincoln Institute of Land Policy
    Tier 2 · Captured 2026-11-07 · Open the source
  9. 9
    Development Community Newsletter, September 2025 (data center ordinance summary)
    City of Mesa, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    Mesa, Arizona noise ordinance, Title 6, Chapter 12
    Noise Pollution Clearinghouse (law library copy of City of Mesa code text)
    Tier 2 · Captured 2026-11-07 · Open the source
  11. 11
    Buy-Through Program for large businesses
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  12. 12
    E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    Notice of Changes to SRP Standard Electric Price Plans
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  14. 14
    Management Recommendations for the February 27, 2025 Special Board Meeting
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  15. 15
    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  16. 16
    E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  17. 17
    SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Council Minutes, Regular Council Meeting, May 17, 2021
    City of Mesa, Office of the City Clerk
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
    Google, published by the Arizona Commerce Authority
    Tier 1 · Captured 2026-11-09 · Open the source
  21. 21
    How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  22. 22
    Google Data Centers: Locations
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  23. 23
    Google 2026 Environmental Report
    Google
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page