Every public record we have for Google Mesa data center (Project Red Hawk)

Mesa, Maricopa County, ArizonaOperatingFirst public 2019Filing entity: Stone Applications LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

21 of 21 records

2025

  • Zoning ruleIn effectDec 10, 2025Maricopa County

    Modernized Maricopa County Zoning Ordinance, data center provisions

    The modernized county zoning ordinance defines data centers and addresses them as an emerging technology use. Reporting on the adopted ordinance states that data centers are allowed in the IND-2 and IND-3 industrial districts, and land not zoned for the use must go through the county rezoning process. A county staff report for a February 2026 hearing states that data centers are a permitted use in the IND-2 district, while noting the ordinance does not specifically contemplate the use, which is why that project sought an overlay clarification.

    Maricopa County Zoning Ordinance (county ordinance P-18), text amendment TA25001

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    News release paragraphs on definitions for emerging technologies including data centers; staff report for cases CPA250009 and Z250027 (2026-02-11 hearing) on IND-2 permitted uses

  • Setback ruleIn effectJul 8, 2025Mesa

    Separation from residential districts, height cap, screening, parking, and sound studies for data centers

    Planning staff described a minimum separation of 400 feet from residential zoning districts or sensitive uses, measured from the data center property to the nearest residential property line, a maximum building height of 60 feet unless an exception is approved through a PAD, screening for mechanical equipment and substations, and parking at 1 space per 5,000 square feet for the first 200,000 square feet and 1 space per 10,000 square feet after that. Staff also described an initial sound study at the nearest residential property line, a post-occupancy sound study within 30 days of the certificate of occupancy, and annual sound studies for the first five years.

    Mesa City Code Section 11-31-36 (standards described by planning staff for Ordinance No. 5957, case PZ25057)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Staff presentation summaries for case PZ25057 (Planning and Zoning Board recommended approval 6-1 on 2025-06-25)

  • Development ruleIn effectJul 8, 2025Mesa

    Backup generator operation and testing notice, Data Centers

    An operator using backup generators must announce any routine operation, including testing, on its website and notify the City of Mesa Public Information Office at least 24 hours in advance. Outside a power outage or a utility demand response event, backup generators may run only between 9:00 a.m. and 5:00 p.m., Monday through Friday, excluding holidays. Systems that can run in parallel with the city electric utility or islanded are subject to a generator interconnection process and study at the operator's cost.

    Mesa City Code Section 11-31-36(G)(4)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Energy section, Example 4, quoting Section 11-31-36(G)(4)(a) to (e) verbatim

  • Development ruleIn effectJul 8, 2025Mesa

    Architectural features for data center buildings

    Every data center building must include at least five of twelve listed architectural features, such as overhangs, canopies, arcades, window shrouds, raised corniced parapets, tower elements, corner glass, sloped roof forms, murals, decorative grilles or screens, and architectural lighting. The standard aims at visual interest at entryways and areas the public sees.

    Mesa City Code Section 11-31-36(F)(5)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Design section quoting Section 11-31-36(F)(5), items i to xii

  • Development ruleIn effectJul 8, 2025Mesa

    Water Consumption and Thermal Management Report and Wastewater Report required with applications

    Every data center development application must include a Water Consumption and Thermal Management Report stating whether the facility is water-cooled or air-cooled, estimated water use in acre feet per year with a monthly breakdown, use in million gallons per day on a typical day and on the highest-use day, the highest instantaneous flow rate, whether high demand can shift to the city's low-demand periods, the number and size of water meters, and proof of a complete Sustainable Water Service Application. A Wastewater Report with proof of a complete Industrial User Survey under Title 8, Chapter 4 is also required.

    Mesa City Code Section 11-31-36(E)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Application requirements quoting Section 11-31-36(E), items 4 and 5

  • Zoning ruleIn effectJul 8, 2025Mesa

    Data Centers, Mesa Zoning Ordinance (Title 11)

    Data centers are allowed as an accessory use in commercial and employment districts and as a principal use in the General Industrial (GI) and Heavy Industrial (HI) districts, but a principal use data center is not allowed by right and needs approval of a Planned Area Development (PAD) Overlay District. A data center that serves only the on-site owner or tenant, does not lease services to third parties, and takes no more than 10 percent of the site's total gross floor area counts as an accessory use and is exempt from the section's standards.

    Mesa City Code Section 11-31-36 (added by Ordinance No. 5957)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Newsletter section on the data center ordinance; council minutes of 2025-07-08, item 8-h (Ordinance No. 5957); code text Section 11-31-36(A)(1) as quoted in the Lincoln Institute resource

2024

  • Utility proceedingDecidedDec 2, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District

    Proposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle

    SRP's elected Board, not the Arizona Corporation Commission, sets its prices through a public pricing process. This process raised overall net revenue 2.4 percent from the November 2025 billing cycle and rewrote the E-67 large load plan: new large load customers must take E-67 and are billed on a minimum demand of 80 percent of their forecasted demand. Management committed to put security requirements in place for new E-67 customers, lasting for the duration of the customer's service agreement.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    SRP Notice of Changes, opening paragraph (Board concluded the process February 27, 2025; +2.4 percent net) and item 5 (E-67 changes); Management Recommendations memorandum, 2025-02-21, item 6 (Credit Provisions for E-67 Customers)

  • Utility proceedingIn effectJan 1, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District

    Buy-Through Program

    A large customer arranges its own generation supply from an eligible third party and SRP delivers it for a Buy-Through Charge, $4.03 per kW from November 1, 2025. The customer needs a minimum annual peak demand of 5 MW and a minimum average monthly load factor of 60 percent, and must be on plan E-63, E-65, or E-67. Total program participation is capped at 200 MW of customer demand.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    SRP Buy-Through Program page, About the program (200 MW cap, 5 MW and 60 percent minimums) and Buy-Through Program Updates (November 1, 2025 charge change)

2021

  • Recorded voteMay 17, 2021Mesa City Council

    Resolution No. 11680: Development Agreement and Sustainable Water Service Agreement with Redale LLC (City file 21-0552)

    6 yes, 1 no. David Luna (Councilmember): yes; Francisco Heredia (Councilmember): yes; Jennifer Duff (Vice Mayor): no; John Giles (Mayor): yes; Julie Spilsbury (Councilmember): yes; Kevin Thompson (Councilmember): yes; Mark Freeman (Councilmember): yes.

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Item 5-h, vote tabulation (motion by Freeman, seconded by Thompson)

2019

  • Public decisionApprovedJul 1, 2019City of Mesa

    City of Mesa, Resolution No. 11372

    Approved and authorized the City Manager to enter into the Development Agreement and Lease with Stone Applications, LLC

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Resolution text (recitals and approval clause), attachment to Legistar File 19-0809

  • Tax agreementApprovedJul 1, 2019City of Mesa

    City of Mesa, Exhibit E to the Development Agreement (Government Property Improvements Lease)

    Form of lease approved with the Development Agreement by Resolution No. 11372 on July 1, 2019; the lease itself is entered on the company's request after a building's certificate of occupancy (Development Agreement Section 5.4)

    Gplet net annual rent:
    $10,000 _per_year
    Gplet rental period:
    25 years
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Exhibit E (GPLET Lease), Sections 4(D), 5(gg), 6(A), 7(G)

  • Public decisionFiledJul 1, 2019City of Mesa

    City of Mesa, Council Report for Legistar File 19-0809

    Staff report recommending approval of the Development Agreement and GPLET Lease

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Council Report, Purpose and Recommendation; Discussion (Development Agreement and Government Property Improvements Lease sections)

  • Development agreementApprovedJul 1, 2019City of Mesa

    City of Mesa, Legistar File 19-0809; approved by Resolution No. 11372

    Approved and authorized by Resolution No. 11372 on July 1, 2019

    Milestone minimum capital investment:
    $800 million
    Water allowance initial:
    1,120 acre_feet_per_year
    Milestone minimum taxable construction costs:
    $240 million
    Full time employee average compensation minimum:
    $65,000 _per_year
    Milestone minimum building gross area:
    500,000 square_feet
    Milestone minimum building gross area:
    250,000 square_feet
    Milestone minimum capital investment:
    $600 million
    Milestone minimum capital investment:
    $1 billion
    Milestone minimum taxable construction costs:
    $180 million
    Milestone minimum taxable construction costs:
    $300 million
    Water allowance maximum:
    4,480 acre_feet_per_year
    Acres:
    186 acres
    Milestone minimum building gross area:
    750,000 square_feet
    Water service peak hour capacity:
    333.3 thousand_gallons_per_hour
    Wastewater peak hour capacity:
    208 thousand_gallons_per_hour
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Development Agreement, parties clause; Recitals A-C; Sections 4.1-4.12, 5.1, 5.4, 6.1-6.6

  • Tax agreementJul 1, 2019Mesa

    Government Property Lease Excise Tax (GPLET) lease (A.R.S. Section 42-6201 et seq.)

    Under the lease form approved with the Development Agreement (Resolution No. 11372), Stone Applications LLC conveys land and improvements to the City of Mesa and leases them back for a Rental Period of 25 years from the first building's certificate of occupancy, at a net rent of $10,000 per year, which the lease states covers the city's administrative costs rather than fair market value. Conveyed property is government property, so the company pays the government property lease excise tax under A.R.S. Section 42-6201 et seq. instead of ad valorem real property tax on the conveyed property. Because the site is outside a Central Business District and a Redevelopment Area, the excise tax is charged at a 150 percent premium over the published excise tax rates, and the site is not eligible for the 8-year full abatement of excise taxes; the council report states this expressly. City staff projected about $32,967,000 in excise taxes over the 25-year term, against an estimated $48,916,134 in real property taxes without the GPLET; the roughly $15.9 million difference is arithmetic on those two city projections, not a figure the city stated. The lease is entered on the company's request after a building's certificate of occupancy (Development Agreement Section 5.4), with a $2,500,000 title policy and closing costs at the company's expense. The Development Agreement's milestones (building area, taxable construction costs, and capital investment minimums at July 1, 2025, 2027, and 2029, plus a $65,000 average compensation floor for project full-time employees) gate the city's water allowance increases. Title to the premises reconveys to the tenant at the end of the lease (Lease Section 34, as referenced in Section 7(G)).

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Development Agreement Section 5.4 and Exhibit E (GPLET Lease) Sections 5(gg), 6(A), 7(G); OED presentation, GPLET slides; council report, Government Property Improvements Lease section, item 6

  • Public decisionFiledJun 27, 2019City of Mesa, Office of Economic Development

    City of Mesa, Office of Economic Development, Study Session Presentation for Legistar File 19-0809

    Staff presentation of the Project Red Hawk agreement terms and the 25-year GPLET analysis

    Real property tax 2019 as farmland:
    $3,604
    Projected total tax revenue 25 year:
    $156.6 million
    Gplet excise tax rate premium:
    150 percent_of_published_rates
    Gplet excise tax projected 25 year:
    $33 million
    Real property tax projected 25 year without gplet:
    $48.9 million
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Presentation slides: City of Mesa Obligations (GPLET); 25-Year GPLET Analysis; Projected Tax Revenue over 25 years

  • RezoningApprovedApr 1, 2019City of Mesa

    City of Mesa, ZON19-00016; Ordinance No. 5502

    Rezoned 187 acres (7100 to 7600 blocks of East Elliot Road; 3100 to 3500 blocks of South Sossaman Road) from LI-PAD-PAD and PEP-PAD-PAD to EO, creating the Red Hawk Employment Opportunity Zone

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Legistar matter 13330 (ZON19-00016 Redhawk), MatterTitle and MatterPassedDate; council report Background section

No date in the record(rules in force and undated records)

  • Development ruleIn effectNo date in the recordMesa

    Offensive, Excessive, and Prohibited Noises, land use sound level limits

    Mesa's general noise chapter sets limiting sound levels by land use district in Table 1, measured as Leq: 60 dBA in residential districts, 65 dBA in commercial or business districts, and 70 dBA in agricultural and industrial districts. Noise exceeding the district level by 5 dBA or more counts as excessive noise under Section 6-12-3, and Section 6-12-4 sets measurement criteria.

    Mesa City Code Title 6, Chapter 12, Sections 6-12-1 to 6-12-6 (Table 1 in Section 6-12-5)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 6-12-5(A), Table 1, Limiting Sound Levels for Land Use Districts; Section 6-12-3; Section 6-12-4

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-67, Standard Price Plan for Large Load Substation Large General Service

    A Large Load Account is an account with a load of 20 MW or more, or reasonably expected to reach 20 MW within five years of first taking service. Accounts first taking service on or after November 1, 2025 must take E-67 and are billed per-kW charges on at least 80 percent of their forecasted demand, whether they use it or not; SRP may reduce the floor where the customer pays for load-serving resources itself, or for economic development reasons. The customer signs an Agreement for Electric Service that specifies the minimum billing demand, the maximum load, and forecasting requirements, and pays a customer-specific facilities charge for its substation on top of the $5,767.02 monthly service charge.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-67 rate book sheet (November 2025 billing cycle), Availability, Special Conditions A to H (Condition B, 80 percent minimum billing demand; Condition E, Agreement for Electric Service), Minimum Bill section

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load

    For customers with maximum billing demand over 5,000 kW who also qualify for E-65 and keep at least 5,000 kW instantaneously interruptible, in exchange for lower charges. Load served under E-66 and the Customized Interruptible Rider together is capped at 205 MW, allocated as SRP decides.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-66 rate book sheet (November 2025 billing cycle), Availability (billing demand over 5,000 kW; 205 MW aggregate cap)

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-65, Standard Price Plan for Substation Large General Service

    Substation-level service with no MW threshold: a $5,767.02 monthly service charge (one meter) plus a customer-specific facilities charge and seasonal on-peak demand charges. Transmission-voltage service above 69 kV earns a 20.1 percent transmission charge reduction.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-65 rate book sheet (November 2025 billing cycle), Availability and monthly service charge table

  • Utility proceedingDecidedNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    Temporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles

    The Board cut FPPAM prices by $0.0038 per kWh for the summer and summer peak 2026 seasons, an overall temporary price decrease of about 3 percent, worth about $5.57 a month to the average residential customer. The decrease applied to all price plans, which includes the large general service plans E-65, E-66 and E-67 whose bills carry the FPPAM component, so large load customers received it on the same per-kWh terms as every other customer. It ran only for the May through October 2026 billing cycles and then reverted to the November 2025 price levels with the November 2026 billing cycle. Management proposed it because the FPPAM balance, the difference between fuel and purchased power costs and what customers have paid toward them, was projected to sit above its Board-approved target range (a surplus of more than $50 million at the end of April 2026).

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    District Board packet for April 13, 2026, minutes of March 26, 2026, consent agenda item B (approval to temporarily decrease FPPAM prices by $0.0038 per kWh effective with the May 2026 billing cycle, summer and summer peak 2026, all price plans); FY26 Annual Report, Electricity Pricing section (Board approved a 3 percent overall summer price decrease through an FPPAM reduction for the May through October 2026 billing cycles, reverting to November 2025 levels)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
    City of Mesa, Office of Economic Development
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
    City of Mesa (Legistar)
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Arizona Technology Council article on the Mesa data center standards
    Arizona Technology Council
    Tier 3 · Captured 2026-11-07 · Open the source
  8. 8
    Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
    Lincoln Institute of Land Policy
    Tier 2 · Captured 2026-11-07 · Open the source
  9. 9
    Development Community Newsletter, September 2025 (data center ordinance summary)
    City of Mesa, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    Mesa, Arizona noise ordinance, Title 6, Chapter 12
    Noise Pollution Clearinghouse (law library copy of City of Mesa code text)
    Tier 2 · Captured 2026-11-07 · Open the source
  11. 11
    Buy-Through Program for large businesses
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  12. 12
    E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    Notice of Changes to SRP Standard Electric Price Plans
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  14. 14
    Management Recommendations for the February 27, 2025 Special Board Meeting
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  15. 15
    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  16. 16
    E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  17. 17
    SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Council Minutes, Regular Council Meeting, May 17, 2021
    City of Mesa, Office of the City Clerk
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
    Google, published by the Arizona Commerce Authority
    Tier 1 · Captured 2026-11-09 · Open the source
  21. 21
    How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  22. 22
    Google Data Centers: Locations
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  23. 23
    Google 2026 Environmental Report
    Google
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page