Every public record we have for Google Journey Data Center (Haskell County)

Haskell, Haskell County, TexasApprovedFirst public 2025Filing entity: Homebound Group LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 5 records · showing tax breaks and payments only ·

2025

  • Tax agreementApprovedJun 24, 2025Haskell County Commissioners Court

    Haskell County Commissioners Court, Haskell County Journey RZ 2025; Texas Tax Code Chapter 312 agreement

    The County entered a Chapter 312 agreement abating 100 percent of county ad valorem taxes except the Interest and Sinking portion, for 10 years per phase, up to four phases, against payments in lieu of taxes (25 percent of would be taxes for Phase 1, 20 percent for Phases 2 to 4) and at least 50 permanent full time jobs

    Pilot phases 2 to 4 share of would be taxes:
    20 percent
    Maximum phases:
    4 phases
    Pilot phase 1 share of would be taxes:
    25 percent
    Phase 1 anticipated capital costs:
    $1 billion
    Annual charitable donation:
    $20,000 per year
    Reinvestment zone area:
    300 acres
    Minimum full time jobs:
    50 jobs
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Recitals (zone designated June 24, 2025); Sections 5, 6, 8(b), 8(e), 8(g), 8(h), 8(i), 17; Exhibits A, B, F

  • Tax agreementJun 24, 2025Haskell County

    Tax abatement agreement (Texas Tax Code Chapter 312)

    The County abates 100 percent of county ad valorem taxes except the Interest and Sinking portion, for 10 years per phase, for up to four phases in the Haskell County Journey RZ 2025 (300.0000 acres). A second abatement term is not provided; the payment in lieu of taxes is 25 percent of the would be county taxes for Phase 1 and 20 percent for each of Phases 2 to 4. At least 50 permanent full time jobs at the Project, stated as a cumulative figure across all phases. Payment in lieu due January 31 after each tax year. A $20,000 donation each abatement year to local governmental or charitable organizations chosen by the County. A Road Use, Maintenance and Crossing Agreement is required within 90 days of the effective date. Phase 1 construction is anticipated to start on or before December 31, 2027 with a completion goal of December 31, 2029; the entity may terminate without liability before December 31, 2029.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement recitals; Sections 5, 6, 8(b), 8(e), 8(h), 8(i); Exhibits A, B, F

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Tax Abatement Agreement between Haskell County and Homebound Group LLC (Haskell County Journey RZ 2025)
    Haskell County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Permit by Rule registration application, Homebound Group LLC, Journey Site, Haskell County (Registration No. 182922, Project No. 404672)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Technical Review, Permit by Rule Registration No. 182922, Journey Site (Homebound Group LLC)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Tax Abatement FAQ, Haskell County
    Haskell County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Data Centers in Texas: lists of all registered Qualifying Data Centers and Qualifying Large Data Center Projects
    Texas Comptroller of Public Accounts
    Tier 1 · Captured 2026-11-09 · Open the source · Archived copy
  6. 6
    Google announces new $40 billion investment in Texas
    Google (The Keyword, Google official blog)
    Tier 2 · Captured 2026-11-09 · Open the source
  7. 7
    Tax Abatement Agreement between Haskell County and Haskell DC Owner, LLC (Haskell County Crusoe RZ 2026)
    Haskell County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Second Amended Notice of Consideration of Tax Abatement Agreement, Haskell County Ranger RZ 2026 (Ascendant Site Solutions LLC)
    Haskell County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Notice of Public Hearing for Reinvestment Zone, Haskell County Ranger RZ 2026
    Haskell County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  10. 10
    TABS project record TABS2025019833, Data Center THM1A, 10357 Loop Road, Haskell, TX
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    TABS project record TABS2026007451, Data Center THM2A, 10357 Loop Road, Haskell, TX
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source