Project File · Public records

Every public record we have for Google Goodnight campus (Armstrong County)

Claude, Armstrong County, TexasUnder constructionFirst public 2025Filing entity: GN DC1, LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

4 of 9 records · showing tax breaks and payments only ·

2025

  • Tax agreementApprovedOct 14, 2025Armstrong County, Texas

    Armstrong County, Texas

    Second agreement: county abates 100 percent of county property taxes on Second Improvements (property first placed on the site after the first agreements abatement periods) for ten years per phase, with a payment in lieu of taxes equal to 15 percent of the county taxes that would otherwise be imposed

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement Sections IV(B), IV(D), V(C); recitals (originals approved November 12, 2024; consolidation approved October 14, 2025)

  • Tax agreementApprovedOct 14, 2025Armstrong County, Texas

    Armstrong County, Texas

    County abates 100 percent of county property taxes on eligible property in each phase for ten full calendar years per phase, with an annual payment in lieu of taxes of $1,360,375 per phase; this consolidated agreement restates the Phase 1 and Phase 2 agreements approved November 12, 2024 as first amended July 14, 2025

    Anticipated capital investment per phase:
    $1 billion
    Site plan section 318 area:
    100 acres
    Site plan total area:
    1,136.8 acres
    Annual pilot per phase:
    $1.4 million
    Site plan section 284 area:
    652.03 acres
    Jobs commitment per phase:
    19 full_time_jobs
    Site plan section 283 area:
    384.77 acres
    Phases anticipated:
    4 phases
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement Sections III, IV(B), IV(D), V(C), IX; recitals (approvals of November 12, 2024, July 14, 2025, October 14, 2025); Exhibit E site plan

  • Tax agreementOct 14, 2025Armstrong County

    Tax Abatement Agreement and Second Tax Abatement Agreement (Chapter 312)

    The county abates 100 percent of county property taxes on Second Improvements, property first placed on the site after the abatement periods under the first agreements, for ten full calendar years per phase. Payment in lieu of taxes equal to 15 percent of all county taxes (including M&O, I&S, and road taxes) that would have been imposed on the certified appraised value of the Second Improvements, per phase per year for ten years. The Jobs Commitment from the first agreement continues to apply during abatement periods under this agreement.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement Sections IV(B), IV(D), V(C); recitals

  • Tax agreementOct 14, 2025Armstrong County

    Tax abatement agreement (Texas Tax Code Chapter 312)

    The county abates 100 percent of county property taxes on eligible real and personal property in each phase for ten full calendar years, beginning the January 1 after the phase achieves commercial operations (the owner may elect an earlier start). A separate abatement runs per phase, for up to eight phases; four phases are currently anticipated. Annual payment in lieu of taxes of $1,360,375 per phase for each of the ten abatement years. Jobs Commitment of 19 full time jobs per phase, measured campus wide from the third year of each phase abatement period. Buildings must remain in place until at least 15 calendar years after commercial operations. Section IX allows assignment of the agreement, in whole or in part, to affiliates and other owners without county consent. Phase 1 commercial operations are due by December 31, 2027, with up to five paid one year extensions.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement Sections III, IV(B), IV(D), V(C), IX; minutes of November 12, 2024

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Amended, Restated, and Consolidated Second Tax Abatement Agreement between Armstrong County, Texas and GN DC1, LLC
    Armstrong County, Texas (posted on the county website)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Armstrong County Commissioners Court Minutes, November 12, 2024
    Armstrong County, Texas (posted on the county website)
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Plain Language Summary for New Source Review, Initial Application for Air Permit Number 182880 (Crusoe Energy Systems LLC, Goodnight Data Center, RN112229901)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Amended Notice of Receipt of Application and Intent to Obtain Air Permit (NORI), Proposed Air Quality Permit Number 182880, GHGPSDTX268, and PSDTX1698: Crusoe Energy Systems LLC, Goodnight Data Center
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Amended, Restated, and Consolidated Tax Abatement Agreement between Armstrong County, Texas and GN DC1, LLC
    Armstrong County, Texas (posted on the county website)
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Order, Docket No. 58881: Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    PUCT Interchange filing index, Project or Docket No. 58881
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    PUCT Interchange filing index, Project or Docket No. 59399
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Google announces new $40 billion investment in Texas
    Google (The Keyword, Google official blog)
    Tier 2 · Captured 2026-11-09 · Open the source
  10. 10
    Governor Abbott, Google Announce $40 Billion Investment In Texas
    Office of the Texas Governor
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    Data Center Locations: Armstrong County, Texas (in development)
    Google
    Tier 2 · Captured 2026-11-09 · Open the source
  12. 12
    Texas Jobs, Energy, Technology, and Innovation (JETI), Office of the Governor, Public Listing as of October 31, 2026
    Office of the Texas Governor
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Armstrong County Commissioners Court page (court roster and posted court documents)
    Armstrong County, Texas
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page