Project File · Public records
Every public record we have for Google Douglas County data center
Lithia Springs, Douglas County, GeorgiaOperatingLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 14 records · showing water supply and use only ·
No date in the record(rules in force and undated records)
Water agreementIssuedNo date in the recordGeorgia Environmental Protection Division
Georgia Environmental Protection Division, NPDES Permit No. GA0038920
- Water flow:
- 600,000 gallons_per_day
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Public Notice No. 2015-15ML (Oct 8, 2015), permittee passage; Public Notice No. 2016-19 ML (Dec 15, 2016), modification passage
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Developments of Regional Impact database: DRI #2508 (IDI2A) initial information form
Georgia Department of Community AffairsTier 1 · Captured 2026-11-09 · Open the source - 2Annual Comprehensive Financial Report for the fiscal year ended December 31, 2023
Douglas County, GeorgiaTier 1 · Captured 2026-11-09 · Open the source - 3Annual Comprehensive Financial Report, fiscal years ended June 30, 2022 and 2021
Douglasville-Douglas County Water and Sewer AuthorityTier 1 · Captured 2026-11-09 · Open the source - 4Public Notice No. 2015-15ML: NPDES Permit Reissuance (Google Inc., GA0038920)
Georgia Environmental Protection DivisionTier 1 · Captured 2026-11-09 · Open the source - 5Public Notice No. 2016-19 ML: NPDES Permit Modification (Google Inc., GA0038920)
Georgia Environmental Protection DivisionTier 1 · Captured 2026-11-09 · Open the source - 6Google Announces $300M Data Center Expansion in Georgia
Elevate Douglas Economic PartnershipTier 1 · Captured 2026-11-09 · Open the source - 7Staff report for special use permit application S2025-13 (March 3 2026 meeting)
Douglas County GeorgiaTier 1 · Captured 2026-11-08 · Open the source - 8Board of Commissioners minutes June 17 2025
Douglas County GeorgiaTier 1 · Captured 2026-11-08 · Open the source - 9Order Approving Revisions to Georgia Power Company's Rules and Regulations, Docket No. 44280, with the PSC news release of January 23, 2025 (Exhibits Q and P)
Georgia Public Service CommissionTier 1 · Captured 2026-11-07 · Open the source - 10Schedule PLL-18, Power and Light Large
Georgia Power CompanyTier 1 · Captured 2026-11-08 · Open the source - 11Stipulation, Docket Nos. 56002 and 56003, Georgia Power 2025 Integrated Resource Plan
Georgia Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 12Electric Service Tariff, Schedule TOU-RN-14, Time of Use, Revenue Neutral (effective with bills for the billing month of June 2026)
Georgia Power CompanyTier 1 · Captured 2026-11-08 · Open the source - 13Order Adopting Stipulation and Granting Certification, Docket Nos. 56298 and 56310
Georgia Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 14Joint Statement of Commission Staff and Georgia Power Company Regarding Large Load Contract Deemed Filed for Purposes of Review, July 27, 2026 (statement dated August 26, 2026)
Georgia Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 15Commission Calendar, November 2026 (Docket No. 57171 hearing, November 12, 2026)
Georgia Public Service CommissionTier 1 · Captured 2026-11-11 · Open the source - 16Douglas County - Google Data Center Locations (Lithia Springs, GA)
GoogleTier 4 · Captured 2026-11-08 · Open the source - 17Douglas County, Georgia - Google Data Centers (locations page)
GoogleTier 4 · Captured 2026-11-09 · Open the source - 18A new partnership to drive renewable energy growth in the U.S.
Google (The Keyword)Tier 4 · Captured 2026-11-09 · Open the source - 19Georgia Power to add 177 MW of solar resources for C&I REDI program
Georgia Power (Southern Company newsroom)Tier 4 · Captured 2026-11-09 · Open the source - 20Helping the Hooch with water conservation at our Douglas County data center
Google Green BlogTier 4 · Captured 2026-11-09 · Open the source - 21Ga. Comp. R. 560-12-2-.117, High-Technology Data Center Equipment exemption administration
Georgia Secretary of State (Rules and Regulations of the State of Georgia)Tier 1 · Captured 2026-11-09 · Open the source - 22U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page