Project File · Public records

Every public record we have for Google Buffalo data center campus

Buffalo, Putnam County, West VirginiaIn permittingFirst public 2026Filing entity: Cumulus Group LLCLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 2 records · showing power and utility only ·

2025

  • Utility proceedingPending before the commissionMar 24, 2025Virginia State Corporation Commission

    Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.

    Under the November 10, 2025 Partial Stipulation (revising the petition as filed): the large load terms apply to new load or expansions at or above 100 MW at an individual site or 150 MW aggregated, contracted after July 1, 2025; initial contract term not less than 14 years with a load ramp of no more than 4 years; monthly billing demand not less than the greater of 80 percent of contract capacity or 80 percent of the highest billing demand in the past 11 months, plus base billing energy of contract capacity times 60 percent times billing hours; collateral as proposed in the petition, negotiable at company discretion. Capacity may be reduced up to 20 percent after year 5 with no exit fee on 42 months notice; larger reductions or termination carry an exit fee equal to the nominal remaining minimum charge over a 1 to 5 year exit fee period, with a company duty to mitigate. No rate change.

    PUR-2025-00057

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Petition paras. 1 and 4 (thresholds, as-filed 12 year term, 80 percent minimum, collateral); Partial Stipulation Exhibit A, pp. 1-5 (para. 1a applicability; paras. 1b-1f term, ramp, billing demand, base billing energy, collateral, reductions and exit fee)

2024

  • Utility proceedingIn effectSep 25, 2024Public Service Commission of West Virginia

    Application for Approval of Revisions to Schedules LCP and IP (Appalachian Power Company and Wheeling Power Company)

    The Large Load Customers section of Schedules L.C.P. and I.P. applies to new load, and to expansions of existing load, contracted after January 1, 2025 where the new load or expansion itself is at least 100 MW at an individual site or 150 MW aggregated. Initial contract term not less than 12 years, commencing after a load ramp of no more than five years; monthly billing demand not less than the greater of 80 percent of contract capacity or 80 percent of the highest billing demand in the past 11 months, plus base billing energy of contract capacity times 60 percent times billing hours; collateral equal to 24 times the previous maximum monthly nonfuel bill, recomputed annually. After the first five years the customer may reduce capacity up to 20 percent in total with no exit fee on 42 months notice; larger reductions or termination carry an exit fee equal to the nominal remaining minimum charge over the remaining term (not less than one, not more than five years), less estimated PJM transmission savings, with a duty to mitigate.

    24-0611-E-T-PW

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Tariff filing of April 7, 2025: Schedule L.C.P. Sheet Nos. 14-3 (Large Load Customers, applicability) and 14-4 (contract term, billing demand, minimum charge, collateral, capacity reductions); Schedule I.P. Sheet Nos. 15-1 to 15-4 (same section); PSC 2024 Management Summary Report, appendix entry for Case No. 24-0611-E-T-PW (filing date)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Votes and minutes

    Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Tariff filing with corrected Schedules L.C.P. and I.P. sheets, Case No. 24-0611-E-T-PW (filed April 7, 2025)
    Public Service Commission of West Virginia
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Petition of Appalachian Power Company for approval of revisions to the Terms and Conditions of Rate Schedule L.P.S., Case PUR-2025-00057
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Partial Stipulation, Case PUR-2025-00057 (filed November 10, 2025)
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Google, Growth and the Next 65 Years: Putnam County Looks Toward a New Economic Era
    Mountaineer Media
    Tier 3 · Captured 2026-11-08 · Open the source
  5. 5
    The Buffalo Data Center: What We Know (facts as of October 18, 2026)
    Putnam Preserve
    Tier 3 · Captured 2026-11-08 · Open the source
  6. 6
    Data Center Promises, Town Plaza Plans, and Candidate Debate
    The Observer (Jefferson County, WV)
    Tier 3 · Captured 2026-11-08 · Open the source
  7. 7
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy