Every public record we have for Flexential Salisbury Data Center

Salisbury, Rowan County, North CarolinaApprovedFiling entity: Trammell Crow CompanyLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 2 records · showing power and utility only ·

2025

  • Utility proceedingPending before the commissionNov 20, 2025North Carolina Utilities Commission

    Application of Duke Energy Carolinas, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement)

    The October 6, 2026 settlement Exhibit 1 is a Large Load Tariff for agreements executed on or after June 1, 2026: a Large Load Customer has total contract demand of 50 MW or more with an expected 12 month rolling average load factor of 80 percent or more, or 150 MW or more at any load factor. Billing demand under Schedule HLF is not less than 75 percent of contract demand; dedicated facilities are funded by a customer CIAC advance, and transmission network upgrades are secured by a letter of credit that steps down after the customer sustains 75 percent of contract demand for three consecutive months. Minimum initial term: the greater of 10 years or 5 years plus the ramp period (under 100 MW), or the greater of 15 years or 10 years plus the ramp (100 MW or more); reduction and termination notice runs 24 to 48 months by size; early termination liquidated damages combine the notification period charges, the net present value of remaining extra facilities charges, and 25 percent of remaining minimum billing demand charges, secured by cash, letter of credit, or parent guarantee. Each agreement must include interruptibility (95 percent of contract load up to 50 hours per year, or 50 percent up to 100 hours) for the ramp plus one year. The tariff leaf is stated effective for service on and after January 1, 2027 if the Commission approves.

    E-7, Sub 1329

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Settlement Exhibit 1, Large Load Tariff, Duke Energy Carolinas NC Original Leaf, pp. 1-3 of the exhibit (definition, CIAC, letter of credit, term, Schedule HLF 75 percent floor, notice periods, liquidated damages, security, reliability provision); Settlement Section II.B.2 (E-100 Sub 208 report commitment)

  • Utility proceedingDecided2025Public Service Commission of South Carolina

    Duke Energy Carolinas, LLC general rate case (Large Load Stipulation)

    The Large Load Stipulation approved December 31, 2025 committed Duke Energy Carolinas, together with Duke Energy Progress, to request a generic large load docket by June 1, 2026 (Docket No. 2026-138-E). The large load discussion in Order No. 2025-769 runs at pages 125 to 129. The stipulation’s other substantive terms were not extracted in this sweep.

    2025-172-E

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Order No. 2025-769 (December 31, 2025) as cited at p. 28 of the Docket No. 2025-172-E filing; large load discussion at order pp. 125-129 per a later filing

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Votes and minutes

    Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Filing in Docket No. 2025-172-E citing Order No. 2025-769 (December 31, 2025)
    Public Service Commission of South Carolina
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Agreement and Stipulation of Settlement on Large Load Tariff, Dockets E-7 Sub 1329 and E-2 Sub 1380 (filed October 6, 2026)
    Duke Energy Carolinas, LLC and Duke Energy Progress, LLC (filing parties)
    Tier 2 · Captured 2026-11-08 · Open the source
  3. 3
    Public Meeting: Q&A from Flexential (Salisbury data center proposal)
    City of Salisbury
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Memorandum to City Council, May 19, 2026: TA2025-10-0013 ordinance amendment, Trammell Crow data storage facility
    City of Salisbury, Land and Development Services
    Tier 1 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page