Skip to content

Project File · Public records

Every public record we have for Equinix Ashburn East (DC21, DC22)

Ashburn, Loudoun County, VirginiaOperatingFirst public 2024Filing entity: Equinix, LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

20 of 20 records

2026

  • Utility proceedingPending before the commissionAug 25, 2026Virginia State Corporation Commission

    Supplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)

    New docket established by Commission order on August 25, 2026 to receive Dominion proposed amendments to its line extension policy, developed with Commission staff under the framework approved in PUR-2026-00056. The amendments are designed to ensure large load customers fund the costs of direct connect transmission facilities needed to serve new or expanding large loads, in situations where those facilities would not be built if not for the large load customer needs. The policy will apply prospectively. No amended policy text had been opened when this row was written, so the specific contribution in aid of construction terms, facility definitions, and any revenue credit are not stated here.

    PUR-2026-00131

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026, Background and direct assignment sections (order establishing this docket entered August 25, 2026; case number PUR-2026-00131; direct connect, but for, and prospective terms)

  • Utility proceedingDecidedMay 1, 2026Virginia State Corporation Commission

    Application of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia

    Transmission cost recovery case (Rider T1) in which the Commission also decided how transmission costs are allocated as large load grows. It approved two changes to Dominion transmission cost allocation method: a forecast adjustment that aligns allocation with rapidly expanding large load growth, and an adjustment incorporating the 85 percent transmission minimum demand charge for certain large load customers from January 1, 2027 (the GS-5 minimum decided in PUR-2025-00058). On the Commission illustration, the amended method cuts the projected Rider T1 increase for a typical residential customer using 1,000 kWh from $2.90 to $0.94 a month. The final order also approved a staff framework to require large load customers to fund direct connect transmission facilities needed for new or expanding large loads, through amendments to Dominion line extension policy in a new supplemental docket, PUR-2026-00131.

    PUR-2026-00056

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Order for Notice and Hearing, May 11, 2026 (application filed May 1, 2026 for Rider T1 under Section 56-585.1 A 4); SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026 (approved forecast adjustment and 85 percent transmission minimum demand adjustment; $2.90 to $0.94 illustration; direct assignment framework; new docket PUR-2026-00131)

  • Utility proceedingPending before the commissionFeb 2, 2026Virginia State Corporation Commission

    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards

    A batch queue for Delivery Point Requests from distribution companies seeking to serve data centers in the Dominion Zone, about 100 MW or more per request and capped at 300 MW. Requests move through Initiation, Feasibility (zoning conformance letter and 30 percent engineering site plan), Development (permits and 100 percent grading plan), and Execution stages. The filing states about 70,000 MW of requests in the queue.

    PUR-2026-00011

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Application filed 2026-02-02 (Submission ID 36180), pages 1-2 (applicability to DP Requests of approximately 100 MW or more; PUR-2025-00058 Final Order at 22-23 directive)

2025

  • Air permitIssuedOct 17, 2025Virginia Department of Environmental Quality

    Virginia Department of Environmental Quality, Registration No. 74189

    Issued (Article 6 minor New Source Review); combined permit superseding the permit dated December 18, 2024; adds three Cummins QSK95-G15 gen-sets at DC-21

    Generator capacity:
    135.15 MW
    Backup generators:
    37 diesel engine gen-sets across DC-21 and DC-22 (Cummins QSK95-G12, QSK95-G15 and QSX15-G9; Kohler KD103V20 and KD27V12; emergency and nonemergency)
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Transmittal letter and attached combined permit, October 17, 2025: DC-21 at 22175 Beaumeade Circle and DC-22 at 22165 Beaumeade Circle, Ashburn, VA 20147; permittee Equinix, LLC, 21551 Beaumeade Circle; application deemed complete October 16, 2025; DEQ issued-permits list row: Equinix LLC (DC-21/DC-22), 74189, 10/17/2025, Article 6 mNSR, Loudoun County

  • Recorded voteAug 11, 2025Loudoun County Board of Equalization

    Affirm the County's 2025 real estate tax assessment of 21673 Beaumeade Circle LLC, 21745 Beaumeade Circle, Ashburn (PIN 060189720000, Appeal ID 6824)

    4 yes, 2 absent. Bob Saltzman (Alternate Member): yes; Chrissie Goodrum (Member): absent; Cliff Keirce (Vice Chairman/Secretary): yes; John Fuog (Member): yes; Kevin Kuesters (Chairman): yes; Sharad Tandale (Member): absent.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    2025 Board of Equalization Annual Report, minutes of the Board of Equalization Hearings, August 11, 2025 (attendance roll, p. 1 of the day's minutes, and the 21673 BEAUMEADE CIRCLE LLC case, Appeal ID 6824)

  • Utility proceedingDecidedMar 31, 2025Virginia State Corporation Commission

    Application of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services

    The Final Order created Schedule GS-5, a rate class for customers demanding 25 MW or more with a load factor of at least 75 percent, effective January 1, 2027. Large customers pay minimum demand charges of 85 percent of contracted distribution demand, 85 percent of contracted transmission demand, and 60 percent of contracted generation demand. The filed GS-3 and GS-4 tariff pages confirm the same minimums reach 25 MW customers on other schedules through Terms and Conditions Section XXVII from January 1, 2027.

    PUR-2025-00058

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    SCC news release, case summary paragraph (GS-5, 25 MW, 85/85/60 minimums, January 1, 2027); Entire Filed Tariff revised 2026-06-01, GS-4 paragraphs I.F, II.B and VIII and GS-3 paragraphs I.G and II.B (high load minimums from 2027-01-01)

  • Zoning ruleIn effectMar 18, 2025Loudoun County

    Data centers moved from by right to special exception in the IP, GI, and MR-HI districts

    Before this amendment, data centers were a by right use in the Industrial Park (IP), General Industry (GI), and Mineral Resources-Heavy Industry (MR-HI) districts. The amendment requires special exception approval in those three districts, and the county states the amendments eliminate data centers as a by right use in the county. Data centers were already a special exception use in the OP, CLI, and PD-RDP districts, and rural policy area districts do not allow data center development.

    ZOAM-2024-0001 and CPAM-2024-0001 (Data Center Standards and Locations Phase 1); Zoning Ordinance Table 3.02.05-1

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    County data center page, Phase 1 amendments section; use status per Zoning Ordinance Table 3.02.05-1

  • Recorded voteMar 18, 2025Loudoun County Board of Supervisors

    Grandfathering Resolution for ZOAM-2024-0001, as amended

    5 yes, 4 no. Caleb Kershner (Supervisor): yes; Juli Briskman (Supervisor): no; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): no; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): no; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): no.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Item 7, p. 9 (Grandfathering Resolution passed 5-4)

  • Recorded voteMar 18, 2025Loudoun County Board of Supervisors

    Adoption of CPAM-2024-0001 and ZOAM-2024-0001, Data Center Standards and Locations, Phase 1 (main motion)

    7 yes, 2 no. Caleb Kershner (Supervisor): no; Juli Briskman (Supervisor): yes; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): no; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Item 7, pp. 9-10 (main motion passed 7-2; Supervisors Kershner and Umstattd opposed)

2024

  • Recorded voteFeb 6, 2024Loudoun County Board of Supervisors

    Resolution approving Loudoun County entering into a Voluntary Settlement Agreement of Annexation and Related Issues with the Town of Leesburg (Compass Creek annexation)

    8 yes, 1 absent. Caleb Kershner (Supervisor): yes; Juli Briskman (Vice Chair): yes; Koran Saines (Supervisor): absent; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Supervisor): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Appendix, Exhibit B (Item A p. 31): motion by Chair Randall, seconded by Vice Chair Briskman; voting list: Supervisors Briskman, Glass, Kershner, Letourneau, Randall, TeKrony, Turner, and Umstattd - Yes; None - No; Supervisor Saines - Absent for the vote

2023

  • Development ruleIn effectDec 13, 2023Loudoun County

    Mechanical equipment screening and buffer planting for data centers

    All ground level and rooftop mechanical equipment must be shown on the site plan and fully screened on all sides, and ground mounted equipment may not sit next to residential property unless a principal building stands between the equipment and that property. In place of the standard buffer table, data centers must plant a Buffer Type C on an earthen berm at least 6 feet high, with a set mix of evergreen and deciduous trees and shrubs.

    Zoning Ordinance Section 4.06.02.D.2 and Section 4.06.02.D.11

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance pp. 283-287, Section 4.06.02.D.2 and Section 4.06.02.D.11

  • Development ruleIn effectDec 13, 2023Loudoun County

    Generator testing hours for data centers next to residential property

    For data centers next to residential property, generator testing is limited to set daytime and early evening windows that change with the season. Outside testing and commissioning, generators may run only for backup or emergency use, and the standard gives way to Commonwealth regulations or permits for the property. Separately, Section 7.05.03.E exempts generator testing noise from the general maximum sound levels, so these hour limits are the control that applies to testing.

    Zoning Ordinance Section 4.06.02.D.8

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance pp. 283-287, Section 4.06.02.D.8

  • Development ruleIn effectDec 13, 2023Loudoun County

    Maximum sound levels by receiving development type, with measurement rules

    The zoning ordinance caps sound at the receiving property for all uses, at all times of day and night. Levels are measured with an integrating sound level meter meeting ANSI S1.43-1997 for Type 1 meters, set to FAST over a 15 second period, with at least 3 samples averaged, taken at the point on the receiving lot line closest to the source with the microphone 5 feet above grade. Exemptions include generator and accessory equipment sounds during an emergency, at a utility request, and during generator testing.

    Zoning Ordinance Section 7.05.03, Table 7.05.03-1

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance pp. 486-487, Section 7.05.03, Table 7.05.03-1; measurement at subsection C; exemptions at subsection E

  • Development ruleIn effectDec 13, 2023Loudoun County

    Noise studies and acoustical screening required for data centers

    Covered projects must file a pre construction noise study at site plan review and a post construction noise study between 1 and 12 months after the first certificate of occupancy, each prepared by a Virginia licensed professional engineer and checked against the Table 7.05.03-1 limits at the nearest point of each property line. For data centers next to residential property, exterior mechanical equipment must be screened on all four sides by an acoustical barrier built with sound proofing material.

    Zoning Ordinance Section 7.05.03.G and Section 4.06.02.D.10

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance p. 487, Section 7.05.03.G; pp. 283-287, Section 4.06.02.D.10

  • Setback ruleIn effectDec 13, 2023Loudoun County

    Setbacks and building massing for data centers next to residential property

    When a data center property sits next to residential property, including across a principal arterial or lesser road, structures must be at least 200 feet from the shared property line and parking at least 50 feet from it. The parking setback must keep existing forest and natural screening undisturbed, or use berms at least 10 feet high with 10 foot tall fencing and plantings on top. A building within 400 feet of the residential line needs height changes at set intervals and a step back of at least 15 feet starting at the top of the second story or 40 feet, whichever is lower.

    Zoning Ordinance Section 4.06.02.D.7

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance pp. 283-287, Section 4.06.02.D.7

  • Development ruleIn effectDec 13, 2023Loudoun County

    Facade design standards for data center buildings

    Principal facades of a data center must use differentiated surfaces at set intervals, and fenestration must cover at least 30 percent of the principal facade surface. A screened mechanical equipment facade may stand in for one required principal facade facing a public road, and each building must include at least one main entrance feature.

    Zoning Ordinance Section 4.06.02.C

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Zoning Ordinance p. 284, Section 4.06.02.C

  • Utility proceedingDecidedJul 3, 2023Virginia State Corporation Commission

    Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services

    This review approved the Contract Dollar Minimum policy now in Terms and Conditions Section XXII.Q: when net distribution investment for new service exceeds $350,000, Dominion may require a written revenue guarantee with a monthly minimum of 50 percent of the customer's lowest anticipated monthly bill, secured by cash deposit, surety bond, or irrevocable letter of credit. The minimum ends when the term expires or revenues collected exceed the net investment.

    PUR-2023-00101

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Entire Filed Tariff revised 2026-06-01, Terms and Conditions Section XXII.Q (effective 2026-01-01)

2022

  • Recorded voteApr 13, 2022Loudoun County Board of Supervisors

    Forward ZCPA-2020-0003, True North Data, to the May 17, 2022 Board of Supervisors Business Meeting for action

    5 yes, 2 no, 2 absent. Caleb A. Kershner (Supervisor): yes; Juli E. Briskman (Supervisor): absent; Koran T. Saines (Supervisor): yes; Kristen C. Umstattd (Supervisor): yes; Matthew F. Letourneau (Supervisor): absent; Michael R. Turner (Supervisor): yes; Phyllis J. Randall (Chair): no; Sylvia R. Glass (Supervisor): yes; Tony Buffington (Supervisor): no.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)

2020

  • Recorded voteDec 10, 2020Loudoun County Planning Commission

    Forward ZCPA-2020-0003, True North Data, to the Board of Supervisors with a recommendation of approval

    5 yes, 3 no, 1 absent. Ad Barnes (Member): no; Eric Combs (Chair): yes; Forest Hayes (Vice Chair): yes; Jane Kirchner (Member): no; Jeff Salmon (Member): yes; John Merrithew (Member): absent; Mark Miller (Member): yes; Michelle Frank (Member): yes; Roger Vance (Member): no.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)

No date in the record(rules in force and undated records)

  • Zoning ruleProposedNo date in the recordLoudoun County

    Phase 2 data center standards and locations, project plan approved, amendments not adopted

    Phase 2 is the follow on round of data center standards and location rules for Loudoun County. The Board approved the project plan on 2025-09-16 and draft text was released at the end of September 2025, but no source read shows the amendments adopted; the county noise page states amendments are anticipated in spring or summer 2027.

    CPAM-2025-0001 and ZOAM-2025-0001 (Data Center Standards and Locations Phase 2)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    County project plan pages; Board TLUC report hosted on loudoun.granicus.com

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Stationary Source Permit to Construct and Operate, Equinix, LLC (Ashburn East), Registration No. 74189 (combined permit)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Issued Air Permits for Data Centers (list as of January 29, 2026)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Loudoun County Zoning Ordinance (official text, eReader)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  4. 4
    Land Use Considerations (county data center page)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  5. 5
    Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
    Dominion Energy Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    SCC Issues Order on DEV Biennial Review 2025
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
    Virginia Electric and Power Company
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    How the SCC Rider T1 Decision Protects Ratepayers
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Order for Notice and Hearing, Case No. PUR-2026-00056
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
    Loudoun County Planning Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
    Loudoun County
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
    Virginia Commission on Local Government (Department of Housing and Community Development)
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Board of Supervisors Business Meeting Minutes, March 18, 2025
    Loudoun County
    Tier 1 · Captured 2026-11-07 · Open the source
  14. 14
    Loudoun County Board of Equalization 2025 Annual Report
    Loudoun County Board of Equalization
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    EDMA Active Air Sites layer (MapServer layer 294), facility records for Registration Nos. 73199, 73233, 73946, 74147, 74189
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page