Project File · Public records
Every public record we have for EdgeCore Mesa campus
Mesa, Maricopa County, ArizonaExpandingFirst public 2023Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
14 of 14 records
2025
Zoning ruleIn effectDec 10, 2025Maricopa County
Modernized Maricopa County Zoning Ordinance, data center provisions
The modernized county zoning ordinance defines data centers and addresses them as an emerging technology use. Reporting on the adopted ordinance states that data centers are allowed in the IND-2 and IND-3 industrial districts, and land not zoned for the use must go through the county rezoning process. A county staff report for a February 2026 hearing states that data centers are a permitted use in the IND-2 district, while noting the ordinance does not specifically contemplate the use, which is why that project sought an overlay clarification.
Maricopa County Zoning Ordinance (county ordinance P-18), text amendment TA25001
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
News release paragraphs on definitions for emerging technologies including data centers; staff report for cases CPA250009 and Z250027 (2026-02-11 hearing) on IND-2 permitted uses
Setback ruleIn effectJul 8, 2025Mesa
Separation from residential districts, height cap, screening, parking, and sound studies for data centers
Planning staff described a minimum separation of 400 feet from residential zoning districts or sensitive uses, measured from the data center property to the nearest residential property line, a maximum building height of 60 feet unless an exception is approved through a PAD, screening for mechanical equipment and substations, and parking at 1 space per 5,000 square feet for the first 200,000 square feet and 1 space per 10,000 square feet after that. Staff also described an initial sound study at the nearest residential property line, a post-occupancy sound study within 30 days of the certificate of occupancy, and annual sound studies for the first five years.
Mesa City Code Section 11-31-36 (standards described by planning staff for Ordinance No. 5957, case PZ25057)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Staff presentation summaries for case PZ25057 (Planning and Zoning Board recommended approval 6-1 on 2025-06-25)
Development ruleIn effectJul 8, 2025Mesa
Backup generator operation and testing notice, Data Centers
An operator using backup generators must announce any routine operation, including testing, on its website and notify the City of Mesa Public Information Office at least 24 hours in advance. Outside a power outage or a utility demand response event, backup generators may run only between 9:00 a.m. and 5:00 p.m., Monday through Friday, excluding holidays. Systems that can run in parallel with the city electric utility or islanded are subject to a generator interconnection process and study at the operator's cost.
Mesa City Code Section 11-31-36(G)(4)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Energy section, Example 4, quoting Section 11-31-36(G)(4)(a) to (e) verbatim
Development ruleIn effectJul 8, 2025Mesa
Architectural features for data center buildings
Every data center building must include at least five of twelve listed architectural features, such as overhangs, canopies, arcades, window shrouds, raised corniced parapets, tower elements, corner glass, sloped roof forms, murals, decorative grilles or screens, and architectural lighting. The standard aims at visual interest at entryways and areas the public sees.
Mesa City Code Section 11-31-36(F)(5)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Design section quoting Section 11-31-36(F)(5), items i to xii
Development ruleIn effectJul 8, 2025Mesa
Water Consumption and Thermal Management Report and Wastewater Report required with applications
Every data center development application must include a Water Consumption and Thermal Management Report stating whether the facility is water-cooled or air-cooled, estimated water use in acre feet per year with a monthly breakdown, use in million gallons per day on a typical day and on the highest-use day, the highest instantaneous flow rate, whether high demand can shift to the city's low-demand periods, the number and size of water meters, and proof of a complete Sustainable Water Service Application. A Wastewater Report with proof of a complete Industrial User Survey under Title 8, Chapter 4 is also required.
Mesa City Code Section 11-31-36(E)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Application requirements quoting Section 11-31-36(E), items 4 and 5
Zoning ruleIn effectJul 8, 2025Mesa
Data Centers, Mesa Zoning Ordinance (Title 11)
Data centers are allowed as an accessory use in commercial and employment districts and as a principal use in the General Industrial (GI) and Heavy Industrial (HI) districts, but a principal use data center is not allowed by right and needs approval of a Planned Area Development (PAD) Overlay District. A data center that serves only the on-site owner or tenant, does not lease services to third parties, and takes no more than 10 percent of the site's total gross floor area counts as an accessory use and is exempt from the section's standards.
Mesa City Code Section 11-31-36 (added by Ordinance No. 5957)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Newsletter section on the data center ordinance; council minutes of 2025-07-08, item 8-h (Ordinance No. 5957); code text Section 11-31-36(A)(1) as quoted in the Lincoln Institute resource
2024
Utility proceedingDecidedDec 2, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District
Proposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle
SRP's elected Board, not the Arizona Corporation Commission, sets its prices through a public pricing process. This process raised overall net revenue 2.4 percent from the November 2025 billing cycle and rewrote the E-67 large load plan: new large load customers must take E-67 and are billed on a minimum demand of 80 percent of their forecasted demand. Management committed to put security requirements in place for new E-67 customers, lasting for the duration of the customer's service agreement.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
SRP Notice of Changes, opening paragraph (Board concluded the process February 27, 2025; +2.4 percent net) and item 5 (E-67 changes); Management Recommendations memorandum, 2025-02-21, item 6 (Credit Provisions for E-67 Customers)
Utility proceedingIn effectJan 1, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District
Buy-Through Program
A large customer arranges its own generation supply from an eligible third party and SRP delivers it for a Buy-Through Charge, $4.03 per kW from November 1, 2025. The customer needs a minimum annual peak demand of 5 MW and a minimum average monthly load factor of 60 percent, and must be on plan E-63, E-65, or E-67. Total program participation is capped at 200 MW of customer demand.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
SRP Buy-Through Program page, About the program (200 MW cap, 5 MW and 60 percent minimums) and Buy-Through Program Updates (November 1, 2025 charge change)
2021
Recorded voteMay 17, 2021Mesa City Council
Resolution No. 11680: Development Agreement and Sustainable Water Service Agreement with Redale LLC (City file 21-0552)
6 yes, 1 no. David Luna (Councilmember): yes; Francisco Heredia (Councilmember): yes; Jennifer Duff (Vice Mayor): no; John Giles (Mayor): yes; Julie Spilsbury (Councilmember): yes; Kevin Thompson (Councilmember): yes; Mark Freeman (Councilmember): yes.
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Item 5-h, vote tabulation (motion by Freeman, seconded by Thompson)
No date in the record(rules in force and undated records)
Development ruleIn effectNo date in the recordMesa
Offensive, Excessive, and Prohibited Noises, land use sound level limits
Mesa's general noise chapter sets limiting sound levels by land use district in Table 1, measured as Leq: 60 dBA in residential districts, 65 dBA in commercial or business districts, and 70 dBA in agricultural and industrial districts. Noise exceeding the district level by 5 dBA or more counts as excessive noise under Section 6-12-3, and Section 6-12-4 sets measurement criteria.
Mesa City Code Title 6, Chapter 12, Sections 6-12-1 to 6-12-6 (Table 1 in Section 6-12-5)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 6-12-5(A), Table 1, Limiting Sound Levels for Land Use Districts; Section 6-12-3; Section 6-12-4
Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District
E-67, Standard Price Plan for Large Load Substation Large General Service
A Large Load Account is an account with a load of 20 MW or more, or reasonably expected to reach 20 MW within five years of first taking service. Accounts first taking service on or after November 1, 2025 must take E-67 and are billed per-kW charges on at least 80 percent of their forecasted demand, whether they use it or not; SRP may reduce the floor where the customer pays for load-serving resources itself, or for economic development reasons. The customer signs an Agreement for Electric Service that specifies the minimum billing demand, the maximum load, and forecasting requirements, and pays a customer-specific facilities charge for its substation on top of the $5,767.02 monthly service charge.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
E-67 rate book sheet (November 2025 billing cycle), Availability, Special Conditions A to H (Condition B, 80 percent minimum billing demand; Condition E, Agreement for Electric Service), Minimum Bill section
Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District
E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
For customers with maximum billing demand over 5,000 kW who also qualify for E-65 and keep at least 5,000 kW instantaneously interruptible, in exchange for lower charges. Load served under E-66 and the Customized Interruptible Rider together is capped at 205 MW, allocated as SRP decides.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
E-66 rate book sheet (November 2025 billing cycle), Availability (billing demand over 5,000 kW; 205 MW aggregate cap)
Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District
E-65, Standard Price Plan for Substation Large General Service
Substation-level service with no MW threshold: a $5,767.02 monthly service charge (one meter) plus a customer-specific facilities charge and seasonal on-peak demand charges. Transmission-voltage service above 69 kV earns a 20.1 percent transmission charge reduction.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
E-65 rate book sheet (November 2025 billing cycle), Availability and monthly service charge table
Utility proceedingDecidedNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District
Temporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles
The Board cut FPPAM prices by $0.0038 per kWh for the summer and summer peak 2026 seasons, an overall temporary price decrease of about 3 percent, worth about $5.57 a month to the average residential customer. The decrease applied to all price plans, which includes the large general service plans E-65, E-66 and E-67 whose bills carry the FPPAM component, so large load customers received it on the same per-kWh terms as every other customer. It ran only for the May through October 2026 billing cycles and then reverted to the November 2025 price levels with the November 2026 billing cycle. Management proposed it because the FPPAM balance, the difference between fuel and purchased power costs and what customers have paid toward them, was projected to sit above its Board-approved target range (a surplus of more than $50 million at the end of April 2026).
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
District Board packet for April 13, 2026, minutes of March 26, 2026, consent agenda item B (approval to temporarily decrease FPPAM prices by $0.0038 per kWh effective with the May 2026 billing cycle, summer and summer peak 2026, all price plans); FY26 Annual Report, Electricity Pricing section (Board approved a 3 percent overall summer price decrease through an FPPAM reduction for the May through October 2026 billing cycles, reverting to November 2025 levels)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
Maricopa County, ArizonaTier 1 · Captured 2026-11-07 · Open the source - 2Arizona Technology Council article on the Mesa data center standards
Arizona Technology CouncilTier 3 · Captured 2026-11-07 · Open the source - 3Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
Lincoln Institute of Land PolicyTier 2 · Captured 2026-11-07 · Open the source - 4Development Community Newsletter, September 2025 (data center ordinance summary)
City of Mesa, ArizonaTier 1 · Captured 2026-11-07 · Open the source - 5Mesa, Arizona noise ordinance, Title 6, Chapter 12
Noise Pollution Clearinghouse (law library copy of City of Mesa code text)Tier 2 · Captured 2026-11-07 · Open the source - 6Buy-Through Program for large businesses
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 7E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 8Notice of Changes to SRP Standard Electric Price Plans
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 9Management Recommendations for the February 27, 2025 Special Board Meeting
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 10E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load (November 2025 billing cycle)
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 11E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
Salt River ProjectTier 1 · Captured 2026-11-07 · Open the source - 12SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
Salt River ProjectTier 1 · Captured 2026-11-08 · Open the source - 13SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
Salt River ProjectTier 1 · Captured 2026-11-08 · Open the source - 14Council Minutes, Regular Council Meeting, May 17, 2021
City of Mesa, Office of the City ClerkTier 1 · Captured 2026-11-08 · Open the source - 15EdgeCore Digital Infrastructure Announces Expansion of Its Metro Phoenix Data Center Market to Over 450 MW
EdgeCore Digital Infrastructure (ACCESS Newswire release via newswire republication)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page