Project File · Public records
Every public record we have for Csquare SFO3
Sunnyvale, Santa Clara County, CaliforniaOperatingLast checked Nov 14, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
6 of 6 records
2026
Utility proceedingPending before the commissionMay 26, 2026California Public Utilities Commission
PG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
PG&E's Tier 3 Advice Letter 7919-E (May 26, 2026) asks for approval of transmission upgrades for GIC San Jose LLC, which requested transmission-level electric service for a data center at 350 W Trimble Rd, San Jose with a maximum forecasted demand of 97.3 MW. The Q5 WG2 sweep put the estimated transmission upgrade cost at $58,280,000 including ITCC, plus $10,726,000 of special facilities (a new 115 kV switching station and a redundant 115 kV line), with facilities expected operational in the third quarter of 2028. No resolution disposing of the advice letter had been located as of the Q5 sweep, so the matter is rowed as pending.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Advice Letter 7919-E (PG&E, dated May 26, 2026): GIC San Jose LLC requested transmission-level electric service for a data center at 350 W Trimble Rd., San Jose, with a maximum forecasted demand of 97.3 MW. Cost and schedule figures are per the Q5 WG2 notes on the same advice letter.
2025
Utility proceedingDecidedAug 4, 2025California Public Utilities Commission
Electric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
Resolution E-5433 (adopted March 19, 2026, issued March 20, 2026) approved with modification an agreement to energize a new 49 MW data center and computing lab for Sunnyvale Technology Partners LLC (c/o Menlo Equities) at 888 Ross Dr, Sunnyvale, with a 115 kV line extension and substation upgrades; operation date June 2027. Annual refunds are capped at 75 percent of the customer's actual annual net revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
Resolution E-5433 (Advice Letter 7667-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5433 text: caption (Advice Letter 7667-E, filed August 4, 2025); date of issuance March 20, 2026; proposed outcome (approves with modification an agreement for a new 49 MW data center and computing lab; refunds limited to 75 percent of net revenues; refund period extended to fifteen years).
Utility proceedingDecidedJul 29, 2025California Public Utilities Commission
Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
Resolution E-5447 (March 19, 2026) approved Advice Letter 7653-E without modification: a non-standard engineering, procurement, and construction agreement under which STACK Infrastructure builds the Ringwood Switching Station approved in Resolution E-5420 and transfers it to PG&E. STACK bears the EPC cost and PG&E's supervision costs. The resolution changes no cost recovery and no refunds; the cost responsibility and refund framework for the 90 MW STACK project sit in Resolution E-5420.
Resolution E-5447 (Advice Letter 7653-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5447 text (Agenda ID 24035, dated March 19, 2026): caption (Advice Letter 7653-E, filed July 29, 2025); proposed outcome (approves Advice Letter 7653-E and the EPC Agreement with STACK Infrastructure); body (no change to the cost recovery or refund framework addressed in E-5420).
Utility proceedingDecidedJul 1, 2025California Public Utilities Commission
Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
Resolution E-5439 (January 15, 2026) approved with modification four agreements to energize a new 90 MW data center for Microsoft Corporation (project SJC02) at 1657 Alviso-Milpitas Rd, San Jose, with 115 kV upgrades at Los Esteros Substation and a new 115 kV line to Microsoft's substation. Microsoft pays all up-front costs and construction is on an actual-cost basis; operation date January 2027. As in the other exceptional cases, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
Resolution E-5439 (Advice Letter 7635-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5439 text (Agenda ID 23925, Rev. 1, dated January 15, 2026): caption (Advice Letter 7635-E, filed July 1, 2025); proposed outcome (approves with modification four agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues; refund period to fifteen years).
Utility proceedingDecidedApr 18, 2025California Public Utilities Commission
Electric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
Resolution E-5420 (adopted October 30, 2025, issued November 7, 2025) approved with modification two agreements to energize a new 90 MW data center for STACK Infrastructure (SI SVY01PG&E, LLC) at 2400 Ringwood Ave, San Jose, including a new 115 kV Ringwood substation; estimated facilities cost $85.9 million including the income tax component of contribution (ITCC). Departing from the standard refund rule, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution states it is non-precedential for the Rule 30 proceeding (A.24-11-007).
Resolution E-5420 (Advice Letter 7569-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5420 text: caption (Advice Letter 7569-E, filed April 18, 2025); proposed outcome (approves with modification two agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues); body (ITCC component; refund period extended to 15 years).
2024
Utility proceedingPending before the commissionNov 21, 2024California Public Utilities Commission
Application of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
PG&E applied on November 21, 2024 for Electric Rule 30, a tariff for new retail customers taking service at transmission voltage (roughly 50 to 230 kV), a class that previously had no tariff and was served deal by deal through exceptional case resolutions. Decision D.25-07-039 (issued July 28, 2025) partially granted interim implementation: transmission-level customers may take service now if they pay in advance or pay actual costs, and they may voluntarily prefund up to 100 percent of specific transmission network upgrades; new transmission-level customers bear the initial cost of all transmission facilities built for them. Refunds, interest, and repayment of prefunding loans are deferred to the final decision, and repayment is not guaranteed. PG&E's compliance Advice Letter 7671-E was rejected in October 2025 because its prefunding loan did not require the customer to prefund 100 percent of all transmission network upgrades as the decision requires. As filed (not adopted), PG&E proposed a minimum demand charge of 75 percent of contracted peak demand and a 15-year minimum contract term. An ALJ ruling of January 9, 2026 re-established the proceeding schedule on cost allocation; the application remains pending.
A.24-11-007
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
ALJ Ruling Establishing Proceeding Schedule, filed January 9, 2026: procedural background (application filed November 21, 2024) and summary of D.25-07-039 (interim implementation terms; refunds, interest and loan repayment deferred to the final decision). The Advice Letter 7671-E rejection and the as-filed 75 percent minimum demand charge and 15-year term are per the Q5 WG2 notes (Commission disposition letter of November 19, 2025 and party testimony), not from the ruling itself.
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Advice 7919-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Upgrades for GIC San Jose LLC
Pacific Gas and Electric Company (CPUC advice letter)Tier 2 · Captured 2026-11-08 · Open the source - 2Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 3Resolution E-5420: PG&E Advice Letter 7569-E exceptional case, STACK Infrastructure (SI SVY01PG&E, LLC), San Jose
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 4Administrative Law Judge's Ruling Setting Schedule on Cost Allocation Issues in A.24-11-007 (PG&E Electric Rule 30)
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 5Resolution E-5433: PG&E Advice Letter 7667-E exceptional case, Sunnyvale Technology Partners LLC, Sunnyvale
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 6Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 7
- 8EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy