Skip to content

Project File · Public records

Every public record we have for Crusoe Abilene AI factory campus for Microsoft

Abilene, Taylor County, TexasUnder constructionFirst public 2026Last checked Nov 13, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

16 of 16 records

2026

  • Air permitUnder reviewAug 5, 2026Texas Commission on Environmental Quality

    Texas Commission on Environmental Quality, 182126; PSDTX1688; GHGPSDTX263

    Executive director preliminary decision to issue a draft permit (Notice of Application and Preliminary Decision, notice issued August 5, 2026); permit not yet issued and the application remains on TCEQ's pending list

    Facility coordinates stated:
    32.50792, -99.77722
    Permit scope description:
    additional power generation equipment for onsite consumption in data center buildings
    Proposed emissions so2:
    233.9 tons_per_year
    Proposed emissions nox:
    760.33 tons_per_year
    Proposed emissions voc:
    815.59 tons_per_year
    Application submitted on:
    2025-11-07
    Facility street address:
    615 Farm-to-Market Road 2404, Abilene, Taylor County, Texas 79601
    Proposed emissions pm2 5:
    313.2 tons_per_year
    Proposed emissions co:
    870.07 tons_per_year
    Nori notice issued on:
    2025-11-19
    Emissions controls stated:
    selective catalytic reduction and oxidation catalysts
    Proposed emissions pm10:
    451.1 tons_per_year
    Proposed emissions haps:
    49.77 tons_per_year
    Napd notice issued on:
    2026-08-05
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    NORI p.1 (application, facility, address); PLS p.1 (facility name, RN, coordinates, emissions); NAPD p.1 and Notice Issuance Date line

  • Public decisionFiledJun 26, 2026Texas Department of Licensing and Regulation

    Texas Department of Licensing and Regulation, TABS2026023929

    Estimated cost as filed:
    $17 million
    Building square footage as filed:
    62,000 sq_ft
    Construction start as filed:
    2026-08-06
    Scope as filed:
    Two power generation support buildings sharing parking
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    TABS project details page, PROJECT and OWNER sections

  • Public decisionIssuedMar 27, 2026

    Company announcement of the campus (Crusoe newsroom release, March 27, 2026)

    Onsite power plant announced:
    900 MW
    Jobs projection announced:
    thousands of additional construction and hundreds of permanent jobs
    Cooling design announced:
    closed-loop non-evaporative liquid cooling
    Buildings announced:
    2
    It load per building announced:
    336 MW
    First building energization expected:
    mid-2027
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Release text: headline, dateline paragraph, Energy-first AI infrastructure section, Economic impact bullet

2025

  • Public decisionApprovedDec 18, 2025City of Abilene

    City of Abilene

    Final approval of ordinances annexing approximately 19.12 acres owned by Lancium Abilene, LLC, 140.97 acres owned by Lancium Abilene II, LLC, and 47.18 acres owned by Lancium Abilene Real Estate, LLC, each accompanied by a municipal services agreement

    Annexed acres lancium abilene real estate llc:
    47.18 acres
    Annexed acres lancium abilene ii llc:
    140.97 acres
    Annexed acres lancium abilene llc:
    19.12 acres
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    December 4 summary (first readings) and December 18 summary (final approval items)

  • Setback ruleProposedDec 18, 2025Abilene

    Adopted 200-foot open-space buffer for the data center campus district

    Ordinance 100-2025 requires a 200-foot buffer, designated on the district exhibit map, to be maintained as open space with all existing vegetation kept. Ordinance 56-2025 replaced the buffer map (Exhibit D) with a revised one (Exhibit E). This is an adopted district condition, not just a staff recommendation as first staged.

    PDD-181 conditions, Ordinance 100-2025 Exhibit A; buffer map amended by Ordinance 56-2025

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Ordinance 100-2025 Exhibit A items (6)-(7); Ordinance 56-2025 Exhibit A

  • Zoning ruleIn effectDec 18, 2025Abilene

    Data center campus zoned through Planned Development District 181

    The Land Development Code use matrix names no data center use, so the Crusoe and Lancium campus runs through its own district ordinance. PDD-181, created by Ordinance 25-2023, has Light Industrial as its base district, and Ordinance 100-2025 permits Data Center: High Performance Computing and Data Center: Bitcoin Mining by right anywhere in the district, under Light Industrial development standards.

    Planned Development District 181 (PDD-181), created by Ordinance No. 25-2023; third amendment Ordinance 100-2025

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Ordinance 100-2025 Exhibit C (permitted uses); Land Development Code Sections 2.3.4.5 and 2.4.2.1 (Municode)

  • Public decisionFiledDec 17, 2025Texas Department of Licensing and Regulation

    Texas Department of Licensing and Regulation, TABS2026008297

    Building square footage as filed:
    738,382 sq_ft
    Estimated completion as filed:
    2027-04-15
    Location address as filed:
    617 FM 2404, Abilene, TX 79601
    Construction start as filed:
    2026-02-21
    Owner as filed:
    Abilene DC9, LLC
    Estimated cost as filed:
    $6.3 billion
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    TABS project details page, PROJECT and OWNER sections

  • Public decisionFiledDec 17, 2025Texas Department of Licensing and Regulation

    Texas Department of Licensing and Regulation, TABS2026008318

    Construction start as filed:
    2026-03-11
    Estimated cost as filed:
    $6.3 billion
    Location address as filed:
    617 FM 2404, Abilene, TX 79601
    Estimated completion as filed:
    2027-05-03
    Owner as filed:
    Abilene DC10, LLC
    Building square footage as filed:
    738,382 sq_ft
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    TABS project details page, PROJECT and OWNER sections

  • Public decisionFiledDec 17, 2025Texas Department of Licensing and Regulation

    Texas Department of Licensing and Regulation, TABS2026008329

    Estimated cost as filed:
    $6.3 billion
    Construction start as filed:
    2026-05-02
    Estimated completion as filed:
    2027-11-11
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    TABS project details page, PROJECT and OWNER sections

  • Public decisionFiledDec 17, 2025Texas Department of Licensing and Regulation

    Texas Department of Licensing and Regulation, TABS2026008308

    Estimated completion as filed:
    2027-09-17
    Estimated cost as filed:
    $6.3 billion
    Construction start as filed:
    2026-04-15
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    TABS project details page, PROJECT and OWNER sections

  • Recorded voteDec 16, 2025Taylor County Commissioners Court

    Adoption of the resolution approving the Taylor County tax abatement agreements for Lancium Clean Campus phases 9 and 10 and the electricity generation plant (Lancium LLC with Abilene DC 9, DC 10, and DC TPP)

    4 yes, 1 no. Brad Birchum (Commissioner, Precinct 3): yes; Chuck Statler (Commissioner, Precinct 4): yes; Kyle Kendrick (Commissioner, Precinct 2): no; Phil Crowley (County Judge): yes; Randall D. Williams (Commissioner, Precinct 1): yes.

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    Minutes of December 16, 2025, item 7D, pp. 5-6: motion by Judge Crowley, seconded by Commissioner Birchum, carried 4-1 with Commissioner Kendrick voting no; all five members present (p. 1).

  • Recorded voteDec 16, 2025Taylor County Commissioners Court

    Resolution approving Tax Abatement Agreement and Second Tax Abatement Agreement with Lancium LLC and Abilene DC 9, LLC (Phase 9), Abilene DC 10, LLC (Phase 10), and Abilene DC TPP, LLC (Electricity Generation Plant)

    1 no. Kyle Kendrick (Commissioner, Precinct 2): no.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Minutes, item 7D: the motion was seconded by Commissioner Birchum and carried with 4-1 vote, Commissioner Kendrick voted No

  • Public decisionApprovedDec 4, 2025City of Abilene

    City of Abilene, Reinvestment Zone No. RZ25-1

    Ordinance on final reading creating City of Abilene Reinvestment Zone No. RZ25-1, encompassing around 614.91 acres, a required step before Chapter 312 tax abatement agreements in the zone

    Reinvestment zone acres:
    614.91 acres
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agenda summary item: creation of Reinvestment Zone No. RZ25-1

  • Tax agreementFiledDec 4, 2025City of Abilene

    City of Abilene

    Agenda item to authorize Tax Abatement Agreements and Second Tax Abatement Agreements for three developments inside Reinvestment Zone RZ25-1: Phase 9 with Abilene DC 9, LLC; Phase 10 with Abilene DC 10, LLC; and an Electricity Generation Plant with Abilene DC TPP, LLC

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    December 4 agenda summary item: multiple Tax Abatement Agreements associated with Lancium facilities within Reinvestment Zone RZ25-1; Comptroller Chapter 312 registry detail file (no RZ25-1 entry)

No date in the record(rules in force and undated records)

  • Development ruleIn effectNo date in the recordAbilene

    Maximum permissible octave band decibel limits at the bounding property line

    At no point at the bounding property line of any use may the sound pressure level exceed the octave band limits in Table 4-3, which run from 86 decibels in the lowest band down to 53 decibels in the highest band, with a limit of 65 decibels on the A scale for daytime. Nighttime levels take a 7-decibel deduction, and the code exempts construction and maintenance noise between 7 a.m. and 9 p.m.

    Abilene Land Development Code Section 4.2.9.2, Table 4-3

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Land Development Code Section 4.2.9.2(a), Table 4-3 (Municode)

  • Development ruleIn effectNo date in the recordAbilene

    General prohibition on unreasonable noise (no decibel limit)

    Section 20-1 declares unlawful any unreasonable loud, disturbing, unnecessary noise that causes material distress, discomfort or injury to persons of ordinary sensibility in the immediate vicinity, and any noise whose character, intensity and duration substantially interferes with the comfort and enjoyment of private homes. It sets no decibel limit; the numeric limits are in the Land Development Code, Section 4.2.9.2.

    Abilene Code of Ordinances Section 20-1 (Chapter 20, Offenses)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Code of Ordinances Section 20-1(a)-(b) (Municode)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    The Totally Easy Agenda: Abilene City Council - December 18, 2025
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    The Totally Easy Agenda: Abilene City Council - December 4, 2025
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    TABS Project Details: Abilene Building 9, Building 9 Core & Shell (CS), TABS2026008297
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    TABS Project Details: Abilene Building 10, Building 10 Core & Shell (CS), TABS2026008318
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Crusoe Announces New 900 MW AI Factory Campus in Abilene, Texas to Support Microsoft AI Infrastructure (2026-03-27)
    Crusoe
    Tier 4 · Captured 2026-11-08 · Open the source
  6. 6
    Chapter 312 Tax Abatement Agreements detail file (registry download), last updated 2026-10-10
    Texas Comptroller of Public Accounts
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    TABS Project Details: Abilene Building 10, Building 10 Tenant Improvement (TI), TABS2026008329
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Plain Language Summary for New Source Review (NSR), Initial Application for Air New Source Review Permit Numbers 182126, GHGPSDTX263 and PSDTX1688, Longhorn Data Center (RN112029061)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Notice of Receipt of Application and Intent to Obtain Air Permit (NORI), Proposed Air Quality Permit Numbers 182126, PSDTX1688, and GHGPSDTX263, Longhorn Data Center Buildings 9 and 10
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  10. 10
    Notice of Application and Preliminary Decision for Air Quality Permits, Proposed Air Quality Permit Numbers 182126, PSDTX1688, and GHGPSDTX263
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    TABS Project Details: Abilene Building 9, Administration and Warehouse Buildings, TABS2026023929
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    TABS Project Details: Abilene Building 9, Building 9 Tenant Improvement (TI), TABS2026008308
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Abilene Ordinance 100-2025, 3rd Amendment to Planned Development District 181
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Abilene Ordinance 56-2025, PDD-181 buffer exhibit amendment
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    Abilene Land Development Code, Section 4.2.9.2, Performance Standards Regulating Noise (Table 4-3)
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    Abilene Code of Ordinances, Section 20-1, Noise control generally
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Abilene Land Development Code, Section 2.3.4.5, Planned Development (PD) District
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Commissioners Court Minutes, December 16, 2025
    Taylor County
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page