Project File · Public records
Every public record we have for Compass Datacenters Ashburn campus
Loudoun County, VirginiaOperatingFirst public 2018Filing entity: Compass Datacenters, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
12 of 28 records · showing votes and minutes only ·
2025
Recorded voteAug 11, 2025Loudoun County Board of Equalization
Affirm the County's 2025 real estate tax assessment of 21673 Beaumeade Circle LLC, 21745 Beaumeade Circle, Ashburn (PIN 060189720000, Appeal ID 6824)
4 yes, 2 absent. Bob Saltzman (Alternate Member): yes; Chrissie Goodrum (Member): absent; Cliff Keirce (Vice Chairman/Secretary): yes; John Fuog (Member): yes; Kevin Kuesters (Chairman): yes; Sharad Tandale (Member): absent.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, minutes of the Board of Equalization Hearings, August 11, 2025 (attendance roll, p. 1 of the day's minutes, and the 21673 BEAUMEADE CIRCLE LLC case, Appeal ID 6824)
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Grandfathering Resolution for ZOAM-2024-0001, as amended
5 yes, 4 no. Caleb Kershner (Supervisor): yes; Juli Briskman (Supervisor): no; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): no; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): no; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, p. 9 (Grandfathering Resolution passed 5-4)
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Adoption of CPAM-2024-0001 and ZOAM-2024-0001, Data Center Standards and Locations, Phase 1 (main motion)
7 yes, 2 no. Caleb Kershner (Supervisor): no; Juli Briskman (Supervisor): yes; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): no; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, pp. 9-10 (main motion passed 7-2; Supervisors Kershner and Umstattd opposed)
2024
Public decisionFiledMar 19, 2024Loudoun County Board of Supervisors
Loudoun County Board of Supervisors, ZCPA-2020-0003
Action Report of the March 19, 2024 Board of Supervisors Business Meeting, Administrative Items Report item c: the Board authorized staff to execute a budget adjustment to disburse $63,960 (LandMARC Sequence # 99083741, Oracle Award # Y01635) to Goose Creek Association pursuant to Proffer VII.K. of ZCPA-2020-0003, True North Data
- Community benefits payment:
- $63,960 cash contribution disbursed to Goose Creek Association pursuant to Proffer VII.K. of ZCPA-2020-0003 (LandMARC Sequence # 99083741, Oracle Award # Y01635), authorized by the Board of Supervisors on March 19, 2024
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the March 19, 2024, Board of Supervisors Business Meeting, Administrative Items Report item c
Recorded voteFeb 6, 2024Loudoun County Board of Supervisors
Resolution approving Loudoun County entering into a Voluntary Settlement Agreement of Annexation and Related Issues with the Town of Leesburg (Compass Creek annexation)
8 yes, 1 absent. Caleb Kershner (Supervisor): yes; Juli Briskman (Vice Chair): yes; Koran Saines (Supervisor): absent; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Supervisor): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Appendix, Exhibit B (Item A p. 31): motion by Chair Randall, seconded by Vice Chair Briskman; voting list: Supervisors Briskman, Glass, Kershner, Letourneau, Randall, TeKrony, Turner, and Umstattd - Yes; None - No; Supervisor Saines - Absent for the vote
2022
Public decisionFiledApr 13, 2022Loudoun County Board of Supervisors
Loudoun County Board of Supervisors, ZCPA-2020-0003
Action Report of the April 13, 2022 Board of Supervisors Public Hearing, Item 10: ZCPA-2020-0003, True North Data (Catoctin). Supervisor Kershner moved, Supervisor Umstattd seconded, that the Board forward the application to the May 17, 2022 Board of Supervisors Business Meeting for action. Motion passed 5-2-2 (Buffington and Randall opposed; Briskman and Letourneau absent for the vote). The Board also directed staff to work with the applicant on proffer updates (an eight-acre conservation easement around the Northern Piedmont Mafic Barren community and a 200-foot Goose Creek buffer)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)
Recorded voteApr 13, 2022Loudoun County Board of Supervisors
Forward ZCPA-2020-0003, True North Data, to the May 17, 2022 Board of Supervisors Business Meeting for action
5 yes, 2 no, 2 absent. Caleb A. Kershner (Supervisor): yes; Juli E. Briskman (Supervisor): absent; Koran T. Saines (Supervisor): yes; Kristen C. Umstattd (Supervisor): yes; Matthew F. Letourneau (Supervisor): absent; Michael R. Turner (Supervisor): yes; Phyllis J. Randall (Chair): no; Sylvia R. Glass (Supervisor): yes; Tony Buffington (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)
2020
Public decisionFiledDec 10, 2020Loudoun County Planning Commission
Loudoun County Planning Commission, ZCPA-2020-0003
Planning Commission Work Session minutes, Item 3: ZCPA-2020-0003, True North Data. Commissioner Miller moved, Commissioner Salmon seconded, to forward the application to the Board of Supervisors with a recommendation of approval, subject to the Proffers dated November 20, 2020. Motion passed 5-3-1 (Barnes, Kirchner and Vance opposed; Merrithew absent). County planning staff could not support the application as proposed
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)
Recorded voteDec 10, 2020Loudoun County Planning Commission
Forward ZCPA-2020-0003, True North Data, to the Board of Supervisors with a recommendation of approval
5 yes, 3 no, 1 absent. Ad Barnes (Member): no; Eric Combs (Chair): yes; Forest Hayes (Vice Chair): yes; Jane Kirchner (Member): no; Jeff Salmon (Member): yes; John Merrithew (Member): absent; Mark Miller (Member): yes; Michelle Frank (Member): yes; Roger Vance (Member): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)
2018
Public decisionFiledSep 6, 2018U.S. Army Corps of Engineers, Norfolk District
U.S. Army Corps of Engineers, Norfolk District, NAO-2013-00808
Federal public notice of a joint application for federal and state permits by Compass Datacenters IAD I LLC for 'Project IAD': discharge of fill into waters of the United States for construction of a data center campus on an approximately 144-acre parcel south of Leesburg; Phase I (39 acres) authorized by General Permit and under construction; Phase II adds six data center buildings; permanent impacts of approximately 0.28 acre of palustrine forested wetlands, 0.75 acre of palustrine emergent wetlands, and 1,097 linear feet of stream beds; the applicant must also obtain a Virginia Water Protection Permit from Virginia DEQ
- Wetland impacts permanent:
- 1.03 acres of wetlands permanently impacted by both project phases (0.28 acre palustrine forested wetlands and 0.75 acre palustrine emergent wetlands)
- Stated in the filing:
- 144 approximate acres of the project parcel as described in the September 6, 2018 federal public notice (southwest of the Dulles Greenway, southeast of Sycolin Road and Gulick Mill Road)
- Stream impacts:
- 1,097 linear feet of stream beds permanently impacted by both project phases (a further 86 linear feet temporarily impacted)
- Buildings:
- 6 additional data center buildings in Phase II of Project IAD (Phase I, 39 acres, was authorized by General Permit and under construction at the notice date)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Federal Public Notice NAO-2013-00808, September 6, 2018, "Waterway and Location of the Proposed Work" and "Proposed Work and Purpose" sections
No date in the record(rules in force and undated records)
Public decisionFiledNo date in the recordLoudoun County Board of Equalization
Loudoun County Board of Equalization
2025 Annual Report: two campus entries are listed in the 2025 commercial appeals settled by the Commissioner of the Revenue office, each with its original 2025 total assessment, the settled total assessment, and decision RED: COMPASS DATACENTERS IAD I LLC, 42247 Thunderball Dr, Leesburg VA 20175 (Little River), total $856,168,970 settled to $422,665,700 (-51%); COMPASS DATACENTERS IAD IB LLC, 42370 Thunderball Dr, Leesburg VA 20175 (Little River), total $95,233,500 settled to $59,130,570 (-38%)
- Assessed total value:
- $856.2 million
- Assessed total value:
- $59.1 million
- Assessed total value:
- $422.7 million
- Assessed total value:
- $95.2 million
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, table '2025 Board of Equalization Commercial Appeals Settled by Commissioner of Revenue Office': COMPASS DATACENTERS IAD I LLC, PIN 089382215000 as printed; COMPASS DATACENTERS IAD IB LLC, PIN 093365404003 as printed (p. 6)
Public decisionFiledNo date in the recordLoudoun County, Virginia
Loudoun County, Virginia, MCPI 194103673000
County Existing Data Center Parcels layer record for the campus parcel: Project TRUE NORTH, owner of record COMPASS DATACENTERS IAD I LLC, 97.116 legal acres, six building permits totaling 547,475 sq ft, status Existing, built status BUILT/UNDER CONSTRUCTION (printed "BULT/UNDER CONSTRUCTION"), zoned OP under the 2023 ordinance with underlying Zoning Case ZMAP-2017-0003
- Parcel acres:
- 97.116 acres
- Buildings:
- 6 data center buildings with building permits on the parcel (permit square footages 300,570; 71,950; 59,244; 39,000; 38,902; 37,809 sq ft); layer built status BUILT/UNDER CONSTRUCTION (printed "BULT/UNDER CONSTRUCTION")
- Floor area:
- 547,475 square feet, total of the six building permits on the parcel (Overall_SQ_FT)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
County Existing Data Center Parcels layer (FeatureServer layer 1), record for MCPI 194103673000, queried 2026-11-09 on the owner name and project name
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2Action Report of the March 19, 2024, Board of Supervisors Business Meeting (County Administrator memorandum, March 21, 2024)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 3Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 4Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 5Stationary Source Permit to Construct and Operate, Compass Datacenters, LLC, Registration No. 74160, November 21, 2025 (amended combined minor New Source Review permit, with transmittal letter)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 6Federal Public Notice NAO-2013-00808, Compass Datacenters IAD I LLC (Project IAD), September 6, 2018
U.S. Army Corps of Engineers, Norfolk DistrictTier 1 · Captured 2026-11-09 · Open the source - 7Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 8Existing Data Center Parcels (county GIS layer), records for MCPI 044261032000 (Pacific Boulevard, Sterling) and MCPI 234371847000 (Compass Creek, Leesburg)
Loudoun County, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 9Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 11Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 12SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 13Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 14How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 15Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 16Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 17Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 18Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 19EDMA Active Air Sites layer (MapServer layer 294), facility record for Registration No. 74160 and statewide Compass name queries
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 20Compass Datacenters Loudoun County campus page (former URL; redirects to the Markets index)
Compass DatacentersTier 4 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page