Project File · Public records
Every public record we have for Compass Datacenters Ashburn campus
Loudoun County, VirginiaOperatingFirst public 2018Filing entity: Compass Datacenters, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
3 of 28 records · showing environmental permits only ·
2025
Air permitIssuedNov 21, 2025Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74160
Issued; amended combined minor New Source Review permit to construct and operate emergency diesel engine gen-sets at a data center at 42255, 42254, 42311 and 42310 Thunderball Drive, Leesburg; supersedes the permit document dated January 20, 2023 and combines the approvals of September 12, 2018, January 20, 2023, and November 21, 2025; based on the permit application dated September 3, 2025, deemed complete November 19, 2025
- Backup generators:
- 75 Cummins Model QSK60-G15 emergency diesel engine gen-sets (Generator 2000DQKAB), rated 2,000 ekW (2,922 bhp) each, in twelve building groups (Ref. Nos. IADI-I-1 through IADI-I-6 and IADI-II-7 through IADI-II-12, Gen-1A through Gen-2C, with IADI-I-5 extending to Gen-3C); originally permitted September 12, 2018
- Backup generators:
- 5 Cummins Model QSK60-G15 emergency diesel engine gen-sets (Generator 2000DQKAB), rated 2,000 ekW (2,922 bhp) each (Ref. Nos. IADI-II-12-Gen-3A through IADI-II-12-Gen-3E), listed as equipment to be constructed; original permit date January 20, 2023
- Backup generators:
- 80 emergency diesel engine gen-sets permitted under the November 21, 2025 combined permit (Ref. Nos. IADI-I-1-Gen-1A through IADI-II-12-Gen-3E)
- Permitted run hours:
- 500 hours per year per gen-set, all purposes (permit Condition 7.a); scheduled maintenance checks and readiness testing are separately capped at 20 hours per year (Condition 7.b)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Transmittal letter and Introduction (pp. 1-2), Stationary Source Permit to Construct and Operate, Registration No. 74160, November 21, 2025
2019
Stormwater permitIssuedJan 8, 2019Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, VAR10M106
Construction general permit coverage (VAR10) for 'True North Phase 2A', 42311 Thunderball Dr, Leesburg; operator of record Compass Datacenters IAD I LLC; development 97.12 acres, disturbed 16.5 acres; status PER_ISSUED; VSMP authority Loudoun County (VSMP-2019-0004)
- Development acres:
- 97.12 acres
- Disturbed acres:
- 16.5 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Stormwater Permits layer (layer 303), record for VAR10M106 (SWC_LOC_FAC_ID 269), queried 2026-11-09 on the operator name and the Thunderball Drive address
2017
Stormwater permitIssuedNov 3, 2017Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, VAR10K766
Construction general permit coverage (VAR10) for 'True North Data', 20632 Sycolin Rd, Leesburg; operator of record Compass Datacenters IAD I LLC; development 105.64 acres, disturbed 36.71 acres; status PER_ISSUED; VSMP authority Loudoun County (VSMP-2017-0098)
- Disturbed acres:
- 36.71 acres
- Development acres:
- 105.64 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Stormwater Permits layer (layer 303), record for VAR10K766 (SWC_LOC_FAC_ID 269), queried 2026-11-09 on the project name and operator name
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2Action Report of the March 19, 2024, Board of Supervisors Business Meeting (County Administrator memorandum, March 21, 2024)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 3Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 4Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 5Stationary Source Permit to Construct and Operate, Compass Datacenters, LLC, Registration No. 74160, November 21, 2025 (amended combined minor New Source Review permit, with transmittal letter)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 6Federal Public Notice NAO-2013-00808, Compass Datacenters IAD I LLC (Project IAD), September 6, 2018
U.S. Army Corps of Engineers, Norfolk DistrictTier 1 · Captured 2026-11-09 · Open the source - 7Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 8Existing Data Center Parcels (county GIS layer), records for MCPI 044261032000 (Pacific Boulevard, Sterling) and MCPI 234371847000 (Compass Creek, Leesburg)
Loudoun County, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 9Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 11Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 12SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 13Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 14How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 15Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 16Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 17Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 18Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 19EDMA Active Air Sites layer (MapServer layer 294), facility record for Registration No. 74160 and statewide Compass name queries
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 20Compass Datacenters Loudoun County campus page (former URL; redirects to the Markets index)
Compass DatacentersTier 4 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page