Project File · Public records
Every public record we have for Compass Datacenters Ashburn campus
Loudoun County, VirginiaOperatingFirst public 2018Filing entity: Compass Datacenters, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
28 of 28 records
2026
Utility proceedingPending before the commissionAug 25, 2026Virginia State Corporation Commission
Supplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)
New docket established by Commission order on August 25, 2026 to receive Dominion proposed amendments to its line extension policy, developed with Commission staff under the framework approved in PUR-2026-00056. The amendments are designed to ensure large load customers fund the costs of direct connect transmission facilities needed to serve new or expanding large loads, in situations where those facilities would not be built if not for the large load customer needs. The policy will apply prospectively. No amended policy text had been opened when this row was written, so the specific contribution in aid of construction terms, facility definitions, and any revenue credit are not stated here.
PUR-2026-00131
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026, Background and direct assignment sections (order establishing this docket entered August 25, 2026; case number PUR-2026-00131; direct connect, but for, and prospective terms)
Utility proceedingDecidedMay 1, 2026Virginia State Corporation Commission
Application of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
Transmission cost recovery case (Rider T1) in which the Commission also decided how transmission costs are allocated as large load grows. It approved two changes to Dominion transmission cost allocation method: a forecast adjustment that aligns allocation with rapidly expanding large load growth, and an adjustment incorporating the 85 percent transmission minimum demand charge for certain large load customers from January 1, 2027 (the GS-5 minimum decided in PUR-2025-00058). On the Commission illustration, the amended method cuts the projected Rider T1 increase for a typical residential customer using 1,000 kWh from $2.90 to $0.94 a month. The final order also approved a staff framework to require large load customers to fund direct connect transmission facilities needed for new or expanding large loads, through amendments to Dominion line extension policy in a new supplemental docket, PUR-2026-00131.
PUR-2026-00056
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Order for Notice and Hearing, May 11, 2026 (application filed May 1, 2026 for Rider T1 under Section 56-585.1 A 4); SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026 (approved forecast adjustment and 85 percent transmission minimum demand adjustment; $2.90 to $0.94 illustration; direct assignment framework; new docket PUR-2026-00131)
Utility proceedingPending before the commissionFeb 2, 2026Virginia State Corporation Commission
Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards
A batch queue for Delivery Point Requests from distribution companies seeking to serve data centers in the Dominion Zone, about 100 MW or more per request and capped at 300 MW. Requests move through Initiation, Feasibility (zoning conformance letter and 30 percent engineering site plan), Development (permits and 100 percent grading plan), and Execution stages. The filing states about 70,000 MW of requests in the queue.
PUR-2026-00011
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Application filed 2026-02-02 (Submission ID 36180), pages 1-2 (applicability to DP Requests of approximately 100 MW or more; PUR-2025-00058 Final Order at 22-23 directive)
2025
Air permitIssuedNov 21, 2025Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74160
Issued; amended combined minor New Source Review permit to construct and operate emergency diesel engine gen-sets at a data center at 42255, 42254, 42311 and 42310 Thunderball Drive, Leesburg; supersedes the permit document dated January 20, 2023 and combines the approvals of September 12, 2018, January 20, 2023, and November 21, 2025; based on the permit application dated September 3, 2025, deemed complete November 19, 2025
- Backup generators:
- 75 Cummins Model QSK60-G15 emergency diesel engine gen-sets (Generator 2000DQKAB), rated 2,000 ekW (2,922 bhp) each, in twelve building groups (Ref. Nos. IADI-I-1 through IADI-I-6 and IADI-II-7 through IADI-II-12, Gen-1A through Gen-2C, with IADI-I-5 extending to Gen-3C); originally permitted September 12, 2018
- Backup generators:
- 5 Cummins Model QSK60-G15 emergency diesel engine gen-sets (Generator 2000DQKAB), rated 2,000 ekW (2,922 bhp) each (Ref. Nos. IADI-II-12-Gen-3A through IADI-II-12-Gen-3E), listed as equipment to be constructed; original permit date January 20, 2023
- Backup generators:
- 80 emergency diesel engine gen-sets permitted under the November 21, 2025 combined permit (Ref. Nos. IADI-I-1-Gen-1A through IADI-II-12-Gen-3E)
- Permitted run hours:
- 500 hours per year per gen-set, all purposes (permit Condition 7.a); scheduled maintenance checks and readiness testing are separately capped at 20 hours per year (Condition 7.b)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Transmittal letter and Introduction (pp. 1-2), Stationary Source Permit to Construct and Operate, Registration No. 74160, November 21, 2025
Recorded voteAug 11, 2025Loudoun County Board of Equalization
Affirm the County's 2025 real estate tax assessment of 21673 Beaumeade Circle LLC, 21745 Beaumeade Circle, Ashburn (PIN 060189720000, Appeal ID 6824)
4 yes, 2 absent. Bob Saltzman (Alternate Member): yes; Chrissie Goodrum (Member): absent; Cliff Keirce (Vice Chairman/Secretary): yes; John Fuog (Member): yes; Kevin Kuesters (Chairman): yes; Sharad Tandale (Member): absent.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, minutes of the Board of Equalization Hearings, August 11, 2025 (attendance roll, p. 1 of the day's minutes, and the 21673 BEAUMEADE CIRCLE LLC case, Appeal ID 6824)
Utility proceedingDecidedMar 31, 2025Virginia State Corporation Commission
Application of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
The Final Order created Schedule GS-5, a rate class for customers demanding 25 MW or more with a load factor of at least 75 percent, effective January 1, 2027. Large customers pay minimum demand charges of 85 percent of contracted distribution demand, 85 percent of contracted transmission demand, and 60 percent of contracted generation demand. The filed GS-3 and GS-4 tariff pages confirm the same minimums reach 25 MW customers on other schedules through Terms and Conditions Section XXVII from January 1, 2027.
PUR-2025-00058
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
SCC news release, case summary paragraph (GS-5, 25 MW, 85/85/60 minimums, January 1, 2027); Entire Filed Tariff revised 2026-06-01, GS-4 paragraphs I.F, II.B and VIII and GS-3 paragraphs I.G and II.B (high load minimums from 2027-01-01)
Zoning ruleIn effectMar 18, 2025Loudoun County
Data centers moved from by right to special exception in the IP, GI, and MR-HI districts
Before this amendment, data centers were a by right use in the Industrial Park (IP), General Industry (GI), and Mineral Resources-Heavy Industry (MR-HI) districts. The amendment requires special exception approval in those three districts, and the county states the amendments eliminate data centers as a by right use in the county. Data centers were already a special exception use in the OP, CLI, and PD-RDP districts, and rural policy area districts do not allow data center development.
ZOAM-2024-0001 and CPAM-2024-0001 (Data Center Standards and Locations Phase 1); Zoning Ordinance Table 3.02.05-1
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
County data center page, Phase 1 amendments section; use status per Zoning Ordinance Table 3.02.05-1
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Grandfathering Resolution for ZOAM-2024-0001, as amended
5 yes, 4 no. Caleb Kershner (Supervisor): yes; Juli Briskman (Supervisor): no; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): no; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): no; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, p. 9 (Grandfathering Resolution passed 5-4)
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Adoption of CPAM-2024-0001 and ZOAM-2024-0001, Data Center Standards and Locations, Phase 1 (main motion)
7 yes, 2 no. Caleb Kershner (Supervisor): no; Juli Briskman (Supervisor): yes; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): no; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, pp. 9-10 (main motion passed 7-2; Supervisors Kershner and Umstattd opposed)
2024
Public decisionFiledMar 19, 2024Loudoun County Board of Supervisors
Loudoun County Board of Supervisors, ZCPA-2020-0003
Action Report of the March 19, 2024 Board of Supervisors Business Meeting, Administrative Items Report item c: the Board authorized staff to execute a budget adjustment to disburse $63,960 (LandMARC Sequence # 99083741, Oracle Award # Y01635) to Goose Creek Association pursuant to Proffer VII.K. of ZCPA-2020-0003, True North Data
- Community benefits payment:
- $63,960 cash contribution disbursed to Goose Creek Association pursuant to Proffer VII.K. of ZCPA-2020-0003 (LandMARC Sequence # 99083741, Oracle Award # Y01635), authorized by the Board of Supervisors on March 19, 2024
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the March 19, 2024, Board of Supervisors Business Meeting, Administrative Items Report item c
Recorded voteFeb 6, 2024Loudoun County Board of Supervisors
Resolution approving Loudoun County entering into a Voluntary Settlement Agreement of Annexation and Related Issues with the Town of Leesburg (Compass Creek annexation)
8 yes, 1 absent. Caleb Kershner (Supervisor): yes; Juli Briskman (Vice Chair): yes; Koran Saines (Supervisor): absent; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Supervisor): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Appendix, Exhibit B (Item A p. 31): motion by Chair Randall, seconded by Vice Chair Briskman; voting list: Supervisors Briskman, Glass, Kershner, Letourneau, Randall, TeKrony, Turner, and Umstattd - Yes; None - No; Supervisor Saines - Absent for the vote
2023
Development ruleIn effectDec 13, 2023Loudoun County
Mechanical equipment screening and buffer planting for data centers
All ground level and rooftop mechanical equipment must be shown on the site plan and fully screened on all sides, and ground mounted equipment may not sit next to residential property unless a principal building stands between the equipment and that property. In place of the standard buffer table, data centers must plant a Buffer Type C on an earthen berm at least 6 feet high, with a set mix of evergreen and deciduous trees and shrubs.
Zoning Ordinance Section 4.06.02.D.2 and Section 4.06.02.D.11
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 283-287, Section 4.06.02.D.2 and Section 4.06.02.D.11
Development ruleIn effectDec 13, 2023Loudoun County
Generator testing hours for data centers next to residential property
For data centers next to residential property, generator testing is limited to set daytime and early evening windows that change with the season. Outside testing and commissioning, generators may run only for backup or emergency use, and the standard gives way to Commonwealth regulations or permits for the property. Separately, Section 7.05.03.E exempts generator testing noise from the general maximum sound levels, so these hour limits are the control that applies to testing.
Zoning Ordinance Section 4.06.02.D.8
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 283-287, Section 4.06.02.D.8
Development ruleIn effectDec 13, 2023Loudoun County
Maximum sound levels by receiving development type, with measurement rules
The zoning ordinance caps sound at the receiving property for all uses, at all times of day and night. Levels are measured with an integrating sound level meter meeting ANSI S1.43-1997 for Type 1 meters, set to FAST over a 15 second period, with at least 3 samples averaged, taken at the point on the receiving lot line closest to the source with the microphone 5 feet above grade. Exemptions include generator and accessory equipment sounds during an emergency, at a utility request, and during generator testing.
Zoning Ordinance Section 7.05.03, Table 7.05.03-1
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 486-487, Section 7.05.03, Table 7.05.03-1; measurement at subsection C; exemptions at subsection E
Development ruleIn effectDec 13, 2023Loudoun County
Noise studies and acoustical screening required for data centers
Covered projects must file a pre construction noise study at site plan review and a post construction noise study between 1 and 12 months after the first certificate of occupancy, each prepared by a Virginia licensed professional engineer and checked against the Table 7.05.03-1 limits at the nearest point of each property line. For data centers next to residential property, exterior mechanical equipment must be screened on all four sides by an acoustical barrier built with sound proofing material.
Zoning Ordinance Section 7.05.03.G and Section 4.06.02.D.10
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance p. 487, Section 7.05.03.G; pp. 283-287, Section 4.06.02.D.10
Setback ruleIn effectDec 13, 2023Loudoun County
Setbacks and building massing for data centers next to residential property
When a data center property sits next to residential property, including across a principal arterial or lesser road, structures must be at least 200 feet from the shared property line and parking at least 50 feet from it. The parking setback must keep existing forest and natural screening undisturbed, or use berms at least 10 feet high with 10 foot tall fencing and plantings on top. A building within 400 feet of the residential line needs height changes at set intervals and a step back of at least 15 feet starting at the top of the second story or 40 feet, whichever is lower.
Zoning Ordinance Section 4.06.02.D.7
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 283-287, Section 4.06.02.D.7
Development ruleIn effectDec 13, 2023Loudoun County
Facade design standards for data center buildings
Principal facades of a data center must use differentiated surfaces at set intervals, and fenestration must cover at least 30 percent of the principal facade surface. A screened mechanical equipment facade may stand in for one required principal facade facing a public road, and each building must include at least one main entrance feature.
Zoning Ordinance Section 4.06.02.C
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance p. 284, Section 4.06.02.C
Utility proceedingDecidedJul 3, 2023Virginia State Corporation Commission
Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
This review approved the Contract Dollar Minimum policy now in Terms and Conditions Section XXII.Q: when net distribution investment for new service exceeds $350,000, Dominion may require a written revenue guarantee with a monthly minimum of 50 percent of the customer's lowest anticipated monthly bill, secured by cash deposit, surety bond, or irrevocable letter of credit. The minimum ends when the term expires or revenues collected exceed the net investment.
PUR-2023-00101
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Entire Filed Tariff revised 2026-06-01, Terms and Conditions Section XXII.Q (effective 2026-01-01)
2022
Public decisionFiledApr 13, 2022Loudoun County Board of Supervisors
Loudoun County Board of Supervisors, ZCPA-2020-0003
Action Report of the April 13, 2022 Board of Supervisors Public Hearing, Item 10: ZCPA-2020-0003, True North Data (Catoctin). Supervisor Kershner moved, Supervisor Umstattd seconded, that the Board forward the application to the May 17, 2022 Board of Supervisors Business Meeting for action. Motion passed 5-2-2 (Buffington and Randall opposed; Briskman and Letourneau absent for the vote). The Board also directed staff to work with the applicant on proffer updates (an eight-acre conservation easement around the Northern Piedmont Mafic Barren community and a 200-foot Goose Creek buffer)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)
Recorded voteApr 13, 2022Loudoun County Board of Supervisors
Forward ZCPA-2020-0003, True North Data, to the May 17, 2022 Board of Supervisors Business Meeting for action
5 yes, 2 no, 2 absent. Caleb A. Kershner (Supervisor): yes; Juli E. Briskman (Supervisor): absent; Koran T. Saines (Supervisor): yes; Kristen C. Umstattd (Supervisor): yes; Matthew F. Letourneau (Supervisor): absent; Michael R. Turner (Supervisor): yes; Phyllis J. Randall (Chair): no; Sylvia R. Glass (Supervisor): yes; Tony Buffington (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)
2020
Public decisionFiledDec 10, 2020Loudoun County Planning Commission
Loudoun County Planning Commission, ZCPA-2020-0003
Planning Commission Work Session minutes, Item 3: ZCPA-2020-0003, True North Data. Commissioner Miller moved, Commissioner Salmon seconded, to forward the application to the Board of Supervisors with a recommendation of approval, subject to the Proffers dated November 20, 2020. Motion passed 5-3-1 (Barnes, Kirchner and Vance opposed; Merrithew absent). County planning staff could not support the application as proposed
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)
Recorded voteDec 10, 2020Loudoun County Planning Commission
Forward ZCPA-2020-0003, True North Data, to the Board of Supervisors with a recommendation of approval
5 yes, 3 no, 1 absent. Ad Barnes (Member): no; Eric Combs (Chair): yes; Forest Hayes (Vice Chair): yes; Jane Kirchner (Member): no; Jeff Salmon (Member): yes; John Merrithew (Member): absent; Mark Miller (Member): yes; Michelle Frank (Member): yes; Roger Vance (Member): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)
2019
Stormwater permitIssuedJan 8, 2019Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, VAR10M106
Construction general permit coverage (VAR10) for 'True North Phase 2A', 42311 Thunderball Dr, Leesburg; operator of record Compass Datacenters IAD I LLC; development 97.12 acres, disturbed 16.5 acres; status PER_ISSUED; VSMP authority Loudoun County (VSMP-2019-0004)
- Development acres:
- 97.12 acres
- Disturbed acres:
- 16.5 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Stormwater Permits layer (layer 303), record for VAR10M106 (SWC_LOC_FAC_ID 269), queried 2026-11-09 on the operator name and the Thunderball Drive address
2018
Public decisionFiledSep 6, 2018U.S. Army Corps of Engineers, Norfolk District
U.S. Army Corps of Engineers, Norfolk District, NAO-2013-00808
Federal public notice of a joint application for federal and state permits by Compass Datacenters IAD I LLC for 'Project IAD': discharge of fill into waters of the United States for construction of a data center campus on an approximately 144-acre parcel south of Leesburg; Phase I (39 acres) authorized by General Permit and under construction; Phase II adds six data center buildings; permanent impacts of approximately 0.28 acre of palustrine forested wetlands, 0.75 acre of palustrine emergent wetlands, and 1,097 linear feet of stream beds; the applicant must also obtain a Virginia Water Protection Permit from Virginia DEQ
- Wetland impacts permanent:
- 1.03 acres of wetlands permanently impacted by both project phases (0.28 acre palustrine forested wetlands and 0.75 acre palustrine emergent wetlands)
- Stated in the filing:
- 144 approximate acres of the project parcel as described in the September 6, 2018 federal public notice (southwest of the Dulles Greenway, southeast of Sycolin Road and Gulick Mill Road)
- Stream impacts:
- 1,097 linear feet of stream beds permanently impacted by both project phases (a further 86 linear feet temporarily impacted)
- Buildings:
- 6 additional data center buildings in Phase II of Project IAD (Phase I, 39 acres, was authorized by General Permit and under construction at the notice date)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Federal Public Notice NAO-2013-00808, September 6, 2018, "Waterway and Location of the Proposed Work" and "Proposed Work and Purpose" sections
2017
Stormwater permitIssuedNov 3, 2017Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, VAR10K766
Construction general permit coverage (VAR10) for 'True North Data', 20632 Sycolin Rd, Leesburg; operator of record Compass Datacenters IAD I LLC; development 105.64 acres, disturbed 36.71 acres; status PER_ISSUED; VSMP authority Loudoun County (VSMP-2017-0098)
- Disturbed acres:
- 36.71 acres
- Development acres:
- 105.64 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Stormwater Permits layer (layer 303), record for VAR10K766 (SWC_LOC_FAC_ID 269), queried 2026-11-09 on the project name and operator name
No date in the record(rules in force and undated records)
Public decisionFiledNo date in the recordLoudoun County Board of Equalization
Loudoun County Board of Equalization
2025 Annual Report: two campus entries are listed in the 2025 commercial appeals settled by the Commissioner of the Revenue office, each with its original 2025 total assessment, the settled total assessment, and decision RED: COMPASS DATACENTERS IAD I LLC, 42247 Thunderball Dr, Leesburg VA 20175 (Little River), total $856,168,970 settled to $422,665,700 (-51%); COMPASS DATACENTERS IAD IB LLC, 42370 Thunderball Dr, Leesburg VA 20175 (Little River), total $95,233,500 settled to $59,130,570 (-38%)
- Assessed total value:
- $856.2 million
- Assessed total value:
- $59.1 million
- Assessed total value:
- $422.7 million
- Assessed total value:
- $95.2 million
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, table '2025 Board of Equalization Commercial Appeals Settled by Commissioner of Revenue Office': COMPASS DATACENTERS IAD I LLC, PIN 089382215000 as printed; COMPASS DATACENTERS IAD IB LLC, PIN 093365404003 as printed (p. 6)
Public decisionFiledNo date in the recordLoudoun County, Virginia
Loudoun County, Virginia, MCPI 194103673000
County Existing Data Center Parcels layer record for the campus parcel: Project TRUE NORTH, owner of record COMPASS DATACENTERS IAD I LLC, 97.116 legal acres, six building permits totaling 547,475 sq ft, status Existing, built status BUILT/UNDER CONSTRUCTION (printed "BULT/UNDER CONSTRUCTION"), zoned OP under the 2023 ordinance with underlying Zoning Case ZMAP-2017-0003
- Parcel acres:
- 97.116 acres
- Buildings:
- 6 data center buildings with building permits on the parcel (permit square footages 300,570; 71,950; 59,244; 39,000; 38,902; 37,809 sq ft); layer built status BUILT/UNDER CONSTRUCTION (printed "BULT/UNDER CONSTRUCTION")
- Floor area:
- 547,475 square feet, total of the six building permits on the parcel (Overall_SQ_FT)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
County Existing Data Center Parcels layer (FeatureServer layer 1), record for MCPI 194103673000, queried 2026-11-09 on the owner name and project name
Zoning ruleProposedNo date in the recordLoudoun County
Phase 2 data center standards and locations, project plan approved, amendments not adopted
Phase 2 is the follow on round of data center standards and location rules for Loudoun County. The Board approved the project plan on 2025-09-16 and draft text was released at the end of September 2025, but no source read shows the amendments adopted; the county noise page states amendments are anticipated in spring or summer 2027.
CPAM-2025-0001 and ZOAM-2025-0001 (Data Center Standards and Locations Phase 2)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
County project plan pages; Board TLUC report hosted on loudoun.granicus.com
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2Action Report of the March 19, 2024, Board of Supervisors Business Meeting (County Administrator memorandum, March 21, 2024)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 3Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 4Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 5Stationary Source Permit to Construct and Operate, Compass Datacenters, LLC, Registration No. 74160, November 21, 2025 (amended combined minor New Source Review permit, with transmittal letter)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 6Federal Public Notice NAO-2013-00808, Compass Datacenters IAD I LLC (Project IAD), September 6, 2018
U.S. Army Corps of Engineers, Norfolk DistrictTier 1 · Captured 2026-11-09 · Open the source - 7Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 8Existing Data Center Parcels (county GIS layer), records for MCPI 044261032000 (Pacific Boulevard, Sterling) and MCPI 234371847000 (Compass Creek, Leesburg)
Loudoun County, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 9Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 11Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 12SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 13Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 14How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 15Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 16Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 17Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 18Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 19EDMA Active Air Sites layer (MapServer layer 294), facility record for Registration No. 74160 and statewide Compass name queries
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 20Compass Datacenters Loudoun County campus page (former URL; redirects to the Markets index)
Compass DatacentersTier 4 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page