Project File · Public records

Every public record we have for Amazon PIT100 Masterplan (Homer City Energy Campus)

Center Township, Indiana County, PennsylvaniaIn permittingFirst public 2026Filing entity: Amazon Data Services, Inc.Last checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

8 of 8 records · showing votes and minutes only ·

2026

  • Public decisionApprovedOct 23, 2026Indiana County Board of Commissioners

    Indiana County Board of Commissioners

    Authorized unanimously (motion by Commissioner Dunlap, seconded by Commissioner Hess)

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Commissioners' Meeting Minutes, October 23, 2026, item "AGREEMENT- GIBSON-THOMAS ENGINEERING - PRELIMINARY LAND DEVELOPMENT PLAN REVIEW FOR AWS AT HOMER CITY ENERGY CAMPUS / PLANNING"

  • Recorded voteOct 23, 2026Indiana County Board of Commissioners

    Agreement with Gibson-Thomas Engineering for engineering review of the PIT100 Masterplan Preliminary Land Development Plan (AWS at Homer City Energy Campus)

    3 yes. Bonni S. Dunlap (Commissioner): yes; R. Michael Keith (Chairman): yes; Sherene Hess (Commissioner): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Commissioners' Meeting Minutes, October 23, 2026: Roll Call (p. 1) lists all three commissioners present; Gibson-Thomas item: "a motion was made by Commissioner Dunlap, seconded by Commissioner Hess and carried unanimously"

  • Public decisionUnder reviewOct 14, 2026Indiana County Office of Planning & Development

    Indiana County Office of Planning & Development

    Application review fees paid to date:
    $216,653
    Open space fee in lieu basis:
    11 acres
    Employees per building peak shift:
    50 employees
    Ninety day review period end:
    2027-01-12
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    ICOPD memo TO: Indiana County Planning Commission, DATE: October 14, 2026, SUBJECT: Preliminary Land Development Plan (PLDP) from Amazon Data Services, Inc. (AWS) with a Project Name of "PIT100 Masterplan"

  • Public decisionUnder reviewSep 9, 2026Indiana County Planning Commission

    Indiana County Planning Commission

    Building floor area each:
    225,000 square feet
    Average salary range:
    80000-100000 per year
    Building height:
    70 feet
    Full buildout completion anticipated:
    2,036
    Data center buildings planned:
    36 buildings
    Phase construction completion bruner:
    2032-06
    Acres to acquire:
    1,100 acres
    Development sites:
    6 sites
    Phase construction completion helen:
    2036-06
    Open space fee in lieu basis:
    34 acres
    Phase construction completion green:
    2030-09
    Phase construction completion west:
    2032-01
    Jobs at full buildout:
    1500-2000 jobs
    Construction start anticipated:
    2026-12
    Phase construction completion rura:
    2030-11
    Phase construction completion harvey gaston:
    2030-04
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Revised Project Narrative: Homer City Energy Campus (revised 9.9.26), pages 1-3, including the Section 301.3 phasing table

  • Public decisionUnder reviewSep 9, 2026Indiana County Planning Commission

    Indiana County Planning Commission

    Cooling water required share of year:
    3 percent of year
    Water treatment facility cost stated:
    $500 million
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    PLDP Presentation, "Homer City Energy Campus, Preliminary Land Development Plan Application, Sept. 9, 2026", slides 4-6 (Proposed Data Center Project; Energy; Water)

  • Public decisionUnder reviewAug 28, 2026Indiana County Planning Commission

    Indiana County Planning Commission, 112265399

    Campus property acres as stated:
    3,200 acres
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Preliminary Stormwater Report, PIT100 - Preliminary Master Plan, Kimley-Horn and Associates, Inc., dated 08/28/2026, sections 1.0-1.1

  • Public decisionUnder reviewAug 28, 2026Indiana County Planning Commission

    Indiana County Planning Commission

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    PIT-100 PLDP Traffic Study Submission (transmittal item 4, described there as the Traffic Mitigation Exhibit)

  • Public decisionUnder reviewAug 28, 2026Indiana County Planning Commission

    Indiana County Planning Commission

    Water supply type as filed:
    Community on-site
    Plan sheet net site area:
    3,373.64 acres
    Property owners as filed:
    Homer City Generation, L.P.; Eagle Acquisitions 1, LLC; Eagle Acquisitions 2, LLC
    Initial application fee:
    $200
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Indiana County Subdivision & Land Development Application, Class V & VI Proposals (Class VI checked; Review Status: Preliminary; Plan Type: New Proposal), with Kimley-Horn transmittal dated 08/28/2026, Job Number 112265291

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Commissioners' Meeting Minutes, Indiana County (PIT100 Masterplan item)
    Indiana County Board of Commissioners
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    PIT100 Masterplan Preliminary Land Development Plan application package (as published by Indiana County)
    Indiana County Office of Planning & Development
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    AWS PLDP Update: PIT100 Masterplan filing notice and review status
    Indiana County Office of Planning & Development
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page