6 of 13 records · showing tax breaks and payments only ·

2026

  • Tax agreementApprovedJan 7, 2026City of Hobart Common Council

    City of Hobart Common Council, Resolution 2026-03

    Approved real property tax abatement and the tax abatement agreement for the portion of the project owned by Hobart Owner, LLC; roll call vote taken, all aye, motion carried (6-0)

    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes p. 9 (journal p. 4164)

  • Tax agreementApprovedJan 7, 2026City of Hobart Common Council

    City of Hobart Common Council, Resolution 2026-02

    Approved real property tax abatement and the tax abatement agreement for the portion of the project owned by Amazon Data Services, Inc.; roll call vote taken, all aye, motion carried (6-0)

    Tax exemption percent:
    100 percent
    Expected jobs:
    400 jobs
    Announced investment:
    $11 billion
    Stated in the filing:
    $37 per hour
    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes pp. 8-9 (journal pp. 4163-4164)

  • Tax agreementApprovedJan 7, 2026City of Hobart Common Council

    City of Hobart Common Council, Resolution 2026-04

    Approved the Enterprise Information Technology Exemption Agreement and the Community Enhancement Agreement with Amazon Data Services, Inc.; roll call vote taken, all aye, motion carried (6-0)

    Tax exemption percent:
    100 percent
    Community benefits payment:
    $47 million
    Stated in the filing:
    $45 million
    Community benefits payment:
    $10 million
    Community benefits payment:
    $2 million per building per year
    Stated in the filing:
    $43 million
    Stated in the filing:
    $40 million
    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes p. 10 (journal p. 4165)

  • Tax agreementJan 7, 2026Hobart

    Real property tax abatement approved by City of Hobart Resolution 2026-02

    100 percent real property tax abatement for each building, per the developer summary in the January 7, 2026 council minutes. Per the minutes: if Amazon fails to make the Community Enhancement Agreement contributions, the City may suspend the real property tax abatements and the enterprise IT exemptions; if no payments are received after a year, the City may terminate the agreements.

    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes pp. 8-9 (journal pp. 4163-4164)

  • Tax agreementJan 7, 2026Hobart

    Real property tax abatement approved by City of Hobart Resolution 2026-03

    100 percent real property tax abatement for each building, on the same terms summarized for the project in the January 7, 2026 council minutes. Same suspension and termination conditions summarized in the minutes for the project agreements.

    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes p. 9 (journal p. 4164)

  • Tax agreementJan 7, 2026Hobart

    Enterprise information technology equipment tax exemption approved by City of Hobart Resolution 2026-04

    100 percent exemption for enterprise information technology equipment for 35 years, per the developer summary in the January 7, 2026 council minutes. Approved together with the Community Enhancement Agreement; suspension and termination conditions summarized in the minutes apply.

    Draft research, not yet verifiedLast checked Nov 10, 2026
    Where it says this

    Minutes pp. 9-10 (journal pp. 4164-4165)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    City of Hobart Common Council Minutes, January 7, 2026
    City of Hobart
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    NiSource release: IURC approval of the NIPSCO GenCo declination of jurisdiction (Cause No. 46183)
    NiSource Inc. (Business Wire)
    Tier 4 · Captured 2026-11-11 · Open the source
  3. 3
    Regulatory Approvals Underscore Strength of NiSource's Customer-Focused Data Center Strategy Supporting Growth in Indiana (NiSource release, republished)
    NiSource Inc. (Business Wire, republished)
    Tier 4 · Captured 2026-11-11 · Open the source · Archived copy
  4. 4
    Amazon plans $15 billion Indiana data center investment
    About Amazon (Amazon)
    Tier 4 · Captured 2026-11-08 · Open the source
  5. 5
    Amazon data center confirmed for Hobart, Mayor Huddlestun (Post-Tribune e-edition)
    Post-Tribune (Chicago Tribune Media Group)
    Tier 3 · Captured 2026-11-08 · Open the source
  6. 6
    Hobart City Council passes tax abatement for data center 6-0
    PanoramaNOW
    Tier 3 · Captured 2026-11-08 · Open the source
  7. 7
    U.S. Census Geocoder (batch geographies endpoint)
    U.S. Census Bureau
    Tier 1 · Captured 2026-11-11 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page