Project File · Public records
Every public record we have for Amazon data center campus at Susquehanna (Cumulus)
Salem Township, Luzerne County, PennsylvaniaExpandingFirst public 2024Filing entity: Amazon Data Services, Inc.Last checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
3 of 7 records · showing water supply and use only ·
2026
Water agreementApprovedMar 12, 2026Susquehanna River Basin Commission
Susquehanna River Basin Commission, Pending No. 2025-159
Modification of the Docket No. 20240901 consumptive use approval for later phases of the campus. Amazon requested a total of 277,000 gpd; DEP's NPDES fact sheet for this campus states that the docket carries modifications issued January 26, 2026 and March 12, 2026 and approves a total consumptive use (30-day average) of 0.129 mgd from Production Well No. 1, Bulk Water Supply, and Public Water Supply
- Water flow:
- 129,000 gallons per day (total approved consumptive use, 30-day average, stated by DEP as 0.129 mgd, from Production Well No. 1, Bulk Water Supply, and Public Water Supply combined)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
SRBC comment-response document (January 28, 2026, updated March 5, 2026), question 2; DEP NPDES Permit Fact Sheet, PA0277118, p. 2
Water agreementUnder reviewFeb 4, 2026Pennsylvania Department of Environmental Protection
Pennsylvania Department of Environmental Protection, PA0277118
- Discharge design flow:
- 0.119 MGD (Outfall 001 design flow: annualized average discharge over 365 days including non-discharge months)
- Water flow:
- 1,500,000 gallons per day (PAWC will-serve amount under average day demand conditions; limited to 1.040 MGD under maximum day demand conditions)
- Water flow:
- 36,000 gallons per day (Production Well No. 1 approved pumping capacity, 25 gallons per minute)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
NPDES Permit Fact Sheet, PA0277118, p. 1 (application received February 4, 2026; accepted February 18, 2026) and Summary of Review, p. 2; draft permit (September 3, 2026 file version)
2024
Water agreementApprovedSep 12, 2024Susquehanna River Basin Commission
Susquehanna River Basin Commission, 20240901
Approval of consumptive use of up to 0.060 mgd (30-day average) from Production Well 1 for evaporative cooling and related incidental uses, with mitigation by payment of the consumptive use mitigation fee
- Water flow:
- 60,000 gallons per day (approved consumptive use cap, 30-day average, stated in the approval as 0.060 mgd, from Production Well 1)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Approval, Docket No. 20240901, pp. 1 to 2 (approval date, approved quantities table, Section 4); application date as recited in the PUC order, Section VI
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Pennsylvania Bulletin, Vol. 55, No. 33 (August 16, 2025)
Commonwealth of PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 2NPDES Permit Fact Sheet, Application No. PA0277118, Amazon Data Services, Inc., ADS Berwick
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 3Public comment responses, Pending No. 2025-159, modification application of Amazon Data Services, Inc.
Susquehanna River Basin CommissionTier 1 · Captured 2026-11-09 · Open the source - 4Docket No. 20240901, Approval: Amazon Data Services, Inc., PHL100 Data Center Campus, Consumptive Use
Susquehanna River Basin CommissionTier 1 · Captured 2026-11-09 · Open the source - 5Order, Application of Pennsylvania-American Water Company, Docket No. A-2024-3051136
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-08 · Open the source - 6Pennsylvania Bulletin, Vol. 56, No. 29 (July 18, 2026)
Commonwealth of PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 7Draft NPDES Permit No. PA0277118, Amazon Data Services, Inc., ADS Berwick
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 8First Amended and Restated Community Benefits Agreement
Salem Township, Luzerne County, PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 9Talen Energy Announces Receipt of Escrowed Funds for Cumulus Data Center Campus Transaction (GlobeNewswire release)
Talen Energy CorporationTier 4 · Captured 2026-11-08 · Open the source - 10Talen Energy Expands Nuclear Energy Relationship with Amazon (press release, Exhibit 99.1 to Form 8-K)
Talen Energy Corporation via SEC EDGARTier 1 · Captured 2026-11-08 · Open the source - 11Governor Josh Shapiro Announces Amazon Plans to Invest $20 Billion in Pennsylvania for AI Infrastructure
Pennsylvania Department of Community and Economic DevelopmentTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page