VermontSenate2025-2026 Biennial SessionBill
S.205: Moratorium on AI data centers until 2030, with study
Official title: An act relating to a temporary moratorium on AI data centers and a report on the construction and operation of AI data centers in Vermont
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed. The official record says: died in committee.
- Filed (done)
- In committee (not reached)
- Passed one chamber (not reached)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
Definition · threshold 100 MW
Applies to: AI data centers
“"AI data center" means a facility that requires greater than 100 megawatts of new load dedicated to AI inference, training, simulation, or synthetic data generation.”
S.205 as introduced, Sec. 1(b)(1)
Pause or moratorium · threshold 100 MW
Applies to: AI data centers
Ends: 2030-07-01.
“To protect the public safety and welfare and safeguard the rights of ratepayers in Vermont, no person shall be permitted to operate an artificial intelligence (AI) data center or to in any way begin site preparation for or commence construction of an AI data center in this State prior to July 1, 2030.”
S.205 as introduced, Sec. 1(a)
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in Vermont (2), not affected
- FirstLight Williston Data CenterOperating
- Tech VaultOperating
Who acted
- CosponsorBongartzSenate
- CosponsorHardySenate
- CosponsorMajorSenate
- CosponsorVyhovskySenate
- Primary sponsorWhiteSenate
More from Vermont
Sources
- 1S.205 as introduced (AI data center moratorium and report)
Vermont General AssemblyTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "S.205: Moratorium on AI data centers until 2030, with study." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/vt-2026-s-205
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page