TVA Large Data Service rate and Capacity Commitment Charge (wholesale rate action)

Where it stands: Decided as of Aug 20, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

TVA removed data center load from the general industrial (manufacturing) rate class and created a wholesale data center rate, effective October 1, 2026. New or expanding data center load above 5 MW carries a Capacity Commitment Charge, paid up front and amortized over three to five years, to recover the cost of building capacity for that load rather than spreading it across the general rate base. TVA expects the average billing impact for data center customers to be about 10 percent, phased over three fiscal years. Huntsville Utilities buys all of its power from TVA, so these are the wholesale terms behind data center service in its territory.

The facts

Regulator
Tennessee Valley Authority Board of Directors
Type
Large load tariff
Utility
Tennessee Valley Authority
State
Tennessee
Status date
Aug 20, 2026
Large-load rules
Yes, for loads of 5 MW or more

Projects served by Tennessee Valley Authority

Related cases and proceedings

Sources

  1. 1
    TVA Board Creates Data Center Rate to Shield Households From AI Power Costs
    Unite.AI
    Tier 3 · Unite.AI report of TVA's August 20, 2026 board action and announcement (approval date; October 1, 2026 effective date; above 5 MW; charge amortization; 10 percent phased impact) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "TVA Large Data Service rate and Capacity Commitment Charge (wholesale rate action)." Last activity 2026-08-20. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-tva-data-center-rate-2026