Skip to content

Utility commission

In the Matter of the Application of Oklahoma Gas and Electric Company for an Order of the Commission Approving its New Extra Large Load Tariff and Terms and Conditions of Service for Extra Large Load Customers and a Regulatory Asset to Recover Costs Associated with Portfolio Optimization Software

Where it stands: Pending before the commission as of Oct 22, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

As proposed by OG&E: the Extra Large Load Tariff applies to new customers expecting demand of at least 75 MW, existing customers adding 75 MW of incremental demand or increasing demand above 125 MW, and existing customers whose profile changes to meet the 75 MW requirement. Terms proposed: a 15 year term with a maximum five year ramp up period, billing minimums, early termination and capacity reduction fees, and strong financial collateral requirements; large load customers pay upfront for 100 percent of the costs to connect to the grid, plus a monthly charge totaling $25 to $30 million per year to be credited to residential customers. Whether large load customers may supply their own or third party generation (the bring your own generation question) is the contested legal issue the Commission sent back for briefing.

The facts

Regulator
Oklahoma Corporation Commission
Docket number
PUD2026-000046
Type
Large load tariff
Utility
Oklahoma Gas & Electric Co
State
Oklahoma
Filed
Jun 1, 2026
Status date
Oct 22, 2026
Large-load rules
Yes, for loads of 75 MW or more

Projects served by Oklahoma Gas & Electric Co

Related cases and proceedings

In the record

  1. Utility case, Jun 2026. Utility case filed: In the Matter of the Application of Oklahoma Gas and Electric Company for an Order of the Commission Approving its New Extra Large Load Tariff and Terms and Conditions of Service for Extra Large Load Customers and a Regulatory Asset to Recover Costs Associated with Portfolio O... Oklahoma Corporation Commission, PUD2026-000046

Sources

  1. 1
    OG&E Proposed Large-Load Tariff Protects Oklahoma households
    Oklahoma Gas and Electric Company
    Tier 4 · OG&E press release, paragraphs on applicability and terms (75 MW and 125 MW tests; 15 year term; five year ramp; billing minimums; termination and capacity reduction fees; collateral; 100 percent upfront connection costs; $25 to $30 million per year residential credit); case style from the OCC Daily Signing Agenda (October 2026), item VI · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "In the Matter of the Application of Oklahoma Gas and Electric Company for an Order of the Commission Approving its New Extra Large Load Tariff and Terms and Conditions of Service for Extra Large Load Customers and a Regulatory Asset to Recover Costs Associated with Portfolio Optimization Software." Last activity 2026-10-22. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-oge-extra-large-load-2026