Idaho Power Company's Petition to Evaluate Class Cost-of-Service Methodology, Consider Alternative Class Cost-of-Service Studies, and Determine Cost of Service Considerations for New Large-Load Customers

Where it stands: Pending before the commission as of Apr 13, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

A single-issue evidentiary docket opened as directed by Order No. 36892 in the 2025 general rate case settlement (IPC-E-25-16). It seeks no rate change and no approval of a specific methodology. Idaho Power’s current 2025 class cost-of-service method functionalizes, classifies and allocates costs on demand, energy and customer drivers; the petition puts four alternatives on the record: EFAC, AED-4CP, Hourly-Informed, and EFAC Production and Transmission Load-Factor Classification. For large loads, the petition identifies concentrated load growth from data centers and industrial customers as a planning and cost allocation challenge, and puts Energy Service Agreements, direct assignment of customer-specific infrastructure costs, and growth-sensitive allocation frameworks on the record. The petition sets no MW threshold.

The facts

Regulator
Idaho Public Utilities Commission
Docket number
IPC-E-26-07
Type
Other
Utility
Idaho Power Co
State
Idaho
Filed
Mar 31, 2026
Status date
Apr 13, 2026
Large-load rules
Yes

Projects served by Idaho Power Co

Related cases and proceedings

In the record

  1. Utility case, Mar 31, 2026. Utility case filed: Idaho Power Company's Petition to Evaluate Class Cost-of-Service Methodology, Consider Alternative Class Cost-of-Service Studies, and Determine Cost of Service Considerations for New Large-Load Customers Idaho Public Utilities Commission, IPC-E-26-07

Sources

  1. 1
    Order No. 36998, Notice of Petition, Case No. IPC-E-26-07
    Idaho Public Utilities Commission
    Tier 1 · Order No. 36998, Notice of Petition, service date April 13, 2026, pages 1-2 (petition filed March 31, 2026; no rate change sought; the four alternatives at Petition paragraphs 14-19; large load growth, Energy Service Agreements and direct assignment at paragraphs 22-25) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Idaho Power Company's Petition to Evaluate Class Cost-of-Service Methodology, Consider Alternative Class Cost-of-Service Studies, and Determine Cost of Service Considerations for New Large-Load Customers." Last activity 2026-04-13. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-idaho-power-ipc-e-26-07