Skip to content

Utility commission

Directive to Electric Distribution Companies regarding data center interconnection requests, pursuant to Executive Order No. 658

Where it stands: Pending before the commission as of Sep 24, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Directive issued under Section 4 of Executive Order 658 (September 8, 2026). Each named electric distribution company must make its own company-specific informational filing in Docket D.P.U. 26-DC by October 23, 2026, listing every load project over 25 MW in its interconnection queue with the facility type, every data center project over 1 MW with queue position, status, and estimated interconnection cost and timeline, the measures it takes or plans to take to eliminate speculative data center projects from the queue (including fees and deposits), the data center queue information it collects, how it will ensure data center projects over 25 MW are legitimate, and what steps it could take to require data centers to bring their own clean energy to meet 100 percent of the data center's demand. No Massachusetts large load tariff exists yet; the large load rate schedule work under Executive Order 654 has no docket number established.

The facts

Regulator
Massachusetts Department of Public Utilities
Docket number
D.P.U. 26-DC
Type
Other
Utility
Fitchburg Gas & Elec Light Co
State
Massachusetts
Filed
Sep 24, 2026
Status date
Sep 24, 2026
Large-load rules
Yes, for loads of 25 MW or more

Related cases and proceedings

In the record

  1. Utility case, Sep 24, 2026. Utility case filed: Directive to Electric Distribution Companies regarding data center interconnection requests, pursuant to Executive Order No. 658 Massachusetts Department of Public Utilities, D.P.U. 26-DC

Sources

  1. 1
    Directive to Electric Distribution Companies regarding data center interconnection requests, pursuant to Executive Order No. 658
    Massachusetts Department of Public Utilities
    Tier 1 · Directive letter (September 24, 2026): direction to the named companies and filing items 1-2 (p. 2), items 3-6 (p. 3), company-specific filing in D.P.U. 26-DC due October 23, 2026 (p. 4) · Open the source
  2. 2
    Executive Order No. 658: Establishing Requirements for Responsible Data Center Development and Operations in Massachusetts
    Commonwealth of Massachusetts (mass.gov)
    Tier 1 · Directive letter (September 24, 2026): direction to the named companies and filing items 1-2 (p. 2), items 3-6 (p. 3), company-specific filing in D.P.U. 26-DC due October 23, 2026 (p. 4) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Directive to Electric Distribution Companies regarding data center interconnection requests, pursuant to Executive Order No. 658." Last activity 2026-09-24. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-fitchburg-dpu-26-dc-2026