Petition of Staff of the Delaware Public Service Commission Regarding a Large Load Tariff to be Promulgated by Delmarva Power & Light Company

Where it stands: Pending before the commission as of Dec 19, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Creates a separate large load class for customers that will use a monthly maximum demand of 25 MW or greater. Order No. 10816 (September 3, 2025) opened the docket, ordered stakeholder workshops to develop the tariff's components, and required Delmarva to file revised tariff pages; the tariff must be in place before any new large load customer of 25 MW or more interconnects. Delmarva filed its proposed tariff on December 19, 2025. A public comment session was held February 25, 2026 and written comments were due March 6, 2026; the Commission's decision is pending.

The facts

Regulator
Delaware Public Service Commission
Docket number
25-0826
Type
Large load tariff
Utility
Delmarva Power & Light Company
State
Delaware
Filed
Aug 28, 2025
Status date
Dec 19, 2025
Large-load rules
Yes, for loads of 25 MW or more

In the record

  1. Utility case, Aug 28, 2025. Utility case filed: Petition of Staff of the Delaware Public Service Commission Regarding a Large Load Tariff to be Promulgated by Delmarva Power & Light Company Delaware Public Service Commission, 25-0826

Sources

  1. 1
    Order No. 10816, Docket No. 25-0826 (large load tariff to be promulgated by Delmarva Power & Light Company)
    Delaware Public Service Commission
    Tier 1 · Order No. 10816 (2025-09-03), ordering paragraphs 1-4; Notice of Public Comment Session (2026-01-12), recital of Order No. 10829 (2025-10-15) and of Delmarva's proposed tariff filed 2025-12-19, and the March 6, 2026 comment deadline · Open the source
  2. 2
    Notice of Public Comment Session, Docket No. 25-0826
    Delaware Public Service Commission
    Tier 1 · Order No. 10816 (2025-09-03), ordering paragraphs 1-4; Notice of Public Comment Session (2026-01-12), recital of Order No. 10829 (2025-10-15) and of Delmarva's proposed tariff filed 2025-12-19, and the March 6, 2026 comment deadline · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Petition of Staff of the Delaware Public Service Commission Regarding a Large Load Tariff to be Promulgated by Delmarva Power & Light Company." Last activity 2025-12-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-delmarva-large-load-tariff-2025