What it is
Creates a separate large load class for customers that will use a monthly maximum demand of 25 MW or greater. Order No. 10816 (September 3, 2025) opened the docket, ordered stakeholder workshops to develop the tariff's components, and required Delmarva to file revised tariff pages; the tariff must be in place before any new large load customer of 25 MW or more interconnects. Delmarva filed its proposed tariff on December 19, 2025. A public comment session was held February 25, 2026 and written comments were due March 6, 2026; the Commission's decision is pending.
The facts
- Regulator
- Delaware Public Service Commission
- Docket number
- 25-0826
- Type
- Large load tariff
- Utility
- Delmarva Power & Light Company
- State
- Delaware
- Filed
- Aug 28, 2025
- Status date
- Dec 19, 2025
- Large-load rules
- Yes, for loads of 25 MW or more
In the record
- Utility case, Aug 28, 2025. Utility case filed: Petition of Staff of the Delaware Public Service Commission Regarding a Large Load Tariff to be Promulgated by Delmarva Power & Light Company Delaware Public Service Commission, 25-0826
Sources
- 1Order No. 10816, Docket No. 25-0826 (large load tariff to be promulgated by Delmarva Power & Light Company)
Delaware Public Service CommissionTier 1 · Order No. 10816 (2025-09-03), ordering paragraphs 1-4; Notice of Public Comment Session (2026-01-12), recital of Order No. 10829 (2025-10-15) and of Delmarva's proposed tariff filed 2025-12-19, and the March 6, 2026 comment deadline · Open the source - 2Notice of Public Comment Session, Docket No. 25-0826
Delaware Public Service CommissionTier 1 · Order No. 10816 (2025-09-03), ordering paragraphs 1-4; Notice of Public Comment Session (2026-01-12), recital of Order No. 10829 (2025-10-15) and of Delmarva's proposed tariff filed 2025-12-19, and the March 6, 2026 comment deadline · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Petition of Staff of the Delaware Public Service Commission Regarding a Large Load Tariff to be Promulgated by Delmarva Power & Light Company." Last activity 2025-12-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-delmarva-large-load-tariff-2025