Utility commission
In the Matter of Black Hills Power, Inc. d/b/a Black Hills Energy for approval to implement an economic flexible load service tariff and amend its energy cost adjustment tariff (Blockchain Interruptible Service Tariff)
Where it stands: In effect as of Jan 29, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Creates the Blockchain Interruptible Service Tariff (BCIS), Section 3B of the company's South Dakota Electric Rate Book, for new customers taking interruptible load of 10,000 kW (10 MW) or more. Service is fully interruptible at the company's discretion on no later than 15 minutes' notice; the company buys the energy, transmission, and ancillary services needed for BCIS customers in the market, and BCIS revenues and costs are removed from the Energy Cost Adjustment so other customers neither pay for nor are harmed by the service. Each customer signs a BCIS Agreement that the company must file with the Commission for approval before service. The company proposed the tariff in April 2025 as an Economic Flexible Load Service Tariff; a stipulation with Commission Staff (January 20, 2026) renamed it and adopted Staff's changes, and the Commission approved it 2-1 on January 27, 2026, with the tariff effective January 29, 2026. The company states the tariff is designed for blockchain operations, which can curtail, and not for conventional data centers, which require firm service.
The facts
- Regulator
- South Dakota Public Utilities Commission
- Docket number
- EL25-019
- Type
- Large load tariff
- Utility
- Black Hills Power
- State
- South Dakota
- Filed
- Apr 28, 2025
- Status date
- Jan 29, 2026
- Large-load rules
- Yes, for loads of 10 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionIn the Matter of Black Hills Power, Inc. d/b/a Black Hills Energy for Approval of a Blockchain Interruptible Electric Service Agreement (CSRE Properties South Dakota, LLC)
In the record
- Utility case, Apr 28, 2025. Utility case filed: In the Matter of Black Hills Power, Inc. d/b/a Black Hills Energy for approval to implement an economic flexible load service tariff and amend its energy cost adjustment tariff (Blockchain Interruptible Service Tariff) South Dakota Public Utilities Commission, EL25-019
Sources
- 1Blockchain Interruptible Service Tariff (BCIS), Section No. 3B, South Dakota Electric Rate Book (Docket EL25-019)
South Dakota Public Utilities CommissionTier 1 · Tariff sheets, Section 3B (10 MW or greater; 15-minute interruption notice; per-agreement Commission approval; filed April 28, 2025, effective January 29, 2026); settlement stipulation (original Economic Flexible Load Service proposal and rename); KOTA report (2-1 approval vote, January 27, 2026) · Open the source - 2Confidential Settlement Stipulation, Docket No. EL25-019 (Black Hills Power and Commission Staff)
South Dakota Public Utilities CommissionTier 1 · Tariff sheets, Section 3B (10 MW or greater; 15-minute interruption notice; per-agreement Commission approval; filed April 28, 2025, effective January 29, 2026); settlement stipulation (original Economic Flexible Load Service proposal and rename); KOTA report (2-1 approval vote, January 27, 2026) · Open the source - 3PUC OKs Black Hills Energy's New Blockchain Power Tariff
KOTA News RadioTier 3 · Tariff sheets, Section 3B (10 MW or greater; 15-minute interruption notice; per-agreement Commission approval; filed April 28, 2025, effective January 29, 2026); settlement stipulation (original Economic Flexible Load Service proposal and rename); KOTA report (2-1 approval vote, January 27, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "In the Matter of Black Hills Power, Inc. d/b/a Black Hills Energy for approval to implement an economic flexible load service tariff and amend its energy cost adjustment tariff (Blockchain Interruptible Service Tariff)." Last activity 2026-01-29. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-black-hills-bcis-2026