Data center pipeline power calculator Beta
How much power would all the data centers planned in a state need?
Short answer: Counting only projects whose records state a capacity (486 of 1,320 tracked in the United States), if every active project is built: about 190,398 MW, of which 17,190 MW is already operating. Projects with no published capacity are not counted, so the real figure is higher.
Add up the announced capacity of every tracked data center project in a state, stage by stage, and choose how likely each stage is to be built.
Beta. A new kind of calculator. The method and every input are shown, but it has not been through a full editor review yet. Tell us what is wrong with the error form.
Data center capacity in the United States
190,398 MW
17,190 MW operating now, plus 173,208 MW from projects not yet operating, at your chances.
Running at a typical 75 percent of capacity, that is as much electricity in a year as about 119,000,000 average U.S. homes.
Undercounts: 834 projects here have no published capacity. Announced capacity is a maximum, not use.
By stage, the United States
| Stage | Projects | With a capacity | Announced MW | Your chance | Counted MW |
|---|---|---|---|---|---|
| Announced | 55 | 29 | 26,328 | 100% | 26,328 |
| Proposed | 124 | 34 | 16,625 | 100% | 16,625 |
| In permitting | 42 | 17 | 19,305 | 100% | 19,305 |
| Approved | 71 | 31 | 25,038 | 100% | 25,038 |
| Under construction | 185 | 95 | 75,541 | 100% | 75,541 |
| Operating | 681 | 242 | 17,190 | 100% | 17,190 |
| Expanding | 53 | 27 | 10,371 | 100% | 10,371 |
| Paused | 9 | 3 | 1,620 | 0% | 0 |
| Cancelled | 31 | 7 | 4,740 | 0% | 0 |
| Stage not known | 69 | 1 | 80 | 0% | 0 |
Each project's capacity is on its Project File with the record it comes from.
How it works
counted MW = Σ (announced MW of the projects in each stage × your chance for that stage)
homes = counted MW × 8,760 hours × typical use ÷ one home's yearly use
Sources
- 1Form EIA-861 final 2025 detailed data files
U.S. Energy Information AdministrationTier 1 · Draft research, not yet verified · Open the source - 2Annual and Peak Electricity Use: History and Future Projections (Powering Intelligence 2026)
EPRITier 2 · Draft research, not yet verified · Open the source
Questions people ask
- How much power would all the planned data centers in the United States need?
- Counting only projects whose records state a capacity (486 of 1,320 tracked in the United States), if every active project is built: about 190,398 MW, of which 17,190 MW is already operating. Projects with no published capacity are not counted, so the real figure is higher.
- Why not just add up every announcement?
- Many announced projects are never built, some are counted twice in press reports, and capacity figures measure different things. This counts each tracked project once, uses the capacity in its own records, and lets you set how likely each stage is to be built.
- Is this a forecast?
- No. It is arithmetic on the records we have and the chances you choose. Utility and grid operator forecasts use their own methods and customer data; where we have them, they are on the place pages.
Calculator version 0.1 (beta). A change to the method gets a new version; the inputs are in the address, so a shared link shows the same result.
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Data center pipeline power calculator." Accessed 2026-11-29. https://datacenterfactcheck.org/calculators/pipeline
Embed this calculator
Paste this code where your page accepts HTML. The calculator runs on this site, so it stays current when the method or the defaults change. Set the height to fit your page.
<iframe src="https://datacenterfactcheck.org/calculators/pipeline/embed" title="Data center pipeline power calculator" width="100%" height="640" loading="lazy"></iframe>